Resolved – (1) That the progress made to date in respect of the Swindon Town Centre regeneration project, now known as "Regent Place", and the intention to commence requisitioning work, be noted. (2) That the Cabinet reaffirms its decision to use Compulsory Purchase powers to promote an Order for the Regent Place Project within the area of Swindon Town Centre identified on the plan attached as Appendix 1 to the joint report. (3) That the Director of Law and Democratic Services and the Director of Property be authorised to take all appropriate actions to promote the proposed Compulsory Purchase Order, referred to in the joint report, on the proposed timeline set out in that report, noting that the costs of such action and arising from it will be fully met by Modus, the Council's development partner for the Regent Place Scheme. The reasons for the decision and alternative options are set out in the report to the meeting. (CM: NM)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Leader of the Council, Cabinet Member for Resources and the Group Director, Resources
Parish / Wards Affected: Central / Eastcott Purpose • To update Cabinet on the steps necessary to promote a Compulsory Purchase Order (CPO) to secure the successful development of Regent Place, Swindon.
Cabinet be requested to: -
• Note this report and the intention to commence requisitioning work;
• Re-affirm its resolution to use Compulsory Purchase powers to promote an Order for the Regent Place scheme within the area of Swindon Town Centre identified, edged black on the plan attached as Appendix 1;
• Authorise the Director of Law and Democratic Services and the Director of Property to take all appropriate actions to promote the Order on the proposed timeline set out in the joint report, noting that the costs of such action and arising from it will be fully met by Modus, the Council’s development partner.
1. Reasons
1.1In order to maintain momentum on this major regeneration project, it is necessary for the Council to commit to the use of its Compulsory Purchase powers.
2. Detail
2.1Attached at Appendix 2 is a briefing note from the Council’s specialist advisors, CBRE, which clearly sets out the stages involved in the Compulsory Purchase Order (CPO) process associated with the “Regent Place” Swindon Town Centre Regeneration Project.
2.2The purpose of this report is to secure the re-affirmation of the Council’s previously stated willingness to use its Compulsory powers in support of this Swindon Town Centre regeneration project. A further detailed report will be presented to Cabinet seeking authority to make the relevant Compulsory Purchase order in due course.
Further information on the subject of this report can be obtained from David Williams on Direct Dial No. 01793 463520 here or Email [email protected]. COMPULSORY PURCHASE ORDER, REGENT PLACE ~ DRAFT
CABINET Date: 15th November 2006
2.3To achieve the position where a detailed report on making the order can be brought forward the requisitioning work should start almost immediately to formally identify all of the potential interests affected by the scheme.
2.4All other elements of the process will flow as per the indicative timescale set out at Appendix 2.
2.5In accordance with changing legislation and guidance, it is now possible to save time and resolve to make an Order in advance of planning permission actually having been granted, i.e. after the planning application has been made a resolution to grant consent has been made by Planning Committee.
2.6There are normally objectives to a Compulsory Purchase Order. Should the planning application be called in by the Secretary of State, one appeal process could deal with both the planning consent and the CPO confirmation and this would negate the potential for sequential delays.
2.7This is the preferred route of our development partner, who is keen to design out inbuilt delay to the project start wherever possible.
Alternative Options • The making of the CPO could be delayed until after the grant of planning permission, but this would give rise to unnecessary delay to the start date of the project, if the CPO process and the Planning process were not run in parallel.
Risk Management Financial and Procurement Implications • There is no financial risk to the Council, as all direct and indirect costs arising from the promotion of the CPO will be met by the Council’s development partner.
Legal / Human Rights Implications • The Director of Law and Democratic Services will make, promote and complete all relevant notices and orders required to progress the CPO process. The CPO process itself is designed to protect people’s individual and human rights.
Links to Corporate Plans and Policies (in particular to Swindon 2010 Promises) • Promise 35.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.