Resolved – (1) That the Director of Law and Democratic Services, in consultation with the Group Director, Resources and Leisure, Group Director Housing and Social Care and the Director of Property and Assets, be authorised to complete a long lease of 125 years at a peppercorn rent and at nil consideration for the disposal of Lease Hill to Housing 21 on the basis set out in the joint report. This will be subject to receipt of appropriate planning permissions to enable the scheme to progress on the terms as set out above. (2) That it be noted that a capital contribution to the scheme of £300,000 will be made from within the Council’s approved Capital Programme in order to secure the provision of an older persons day centre on a long lease on the Lease Hill site. (CM: PG / NM / PY)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member, Health, Housing and Social Care and Director Service Delivery, Adult Social Care and Primary Care Trust
Parish / Wards Affected: Moredon
Purpose • To seek approval for the disposal of the Lease Hill Residential Care Home site to Housing 21 along with a capital contribution of £300,00 in order to secure the redevelopment of that site to provide a 49 unit (34 rented and 15 homebuy) Extra Care Resource Centre.
Recommendation Cabinet is requested to • Authorise the Director of Law and Democratic Services, in consultation with the Group Director, Resources and Leisure, Group Director Housing and Social Care and the Director of Property and Assets to create a long lease of 125 years at a peppercorn rent and at nil consideration for the disposal of Lease Hill to Housing 21 on the basis set out in the joint report. This will be subject to receipt of appropriate planning permissions to enable the scheme to progress on the terms as set out above.
• Note that a capital contribution to the scheme of £300,000 will be made from within the Council’s approved Capital Programme in order to secure the provision of an older persons day centre on a long lease on the Lease Hill site.
1. Reasons 1.1 To greatly assist in the Borough’s plans to deliver Extra Care Housing in Swindon by delivering the first new build scheme in the Borough as part of Promise no 32 in Swindon 2010
1.2£3 million in Housing Corporation grant funding has been approved together with private finance of over £3 million to deliver a state of the art facility for Swindon.
2. Detail
2.1Cabinet , on 14th November 2006, approved the extra care development programme for further schemes in Swindon including the development at Lease Hill. A selection process was followed by way of inviting expressions of
Further information on the subject of this report can be obtained from Louise Barrow on 01793 464323 or Email [email protected]. Lease Hill Site at Moredon
CABINET Date: 12th September 2007
interest and holding interviews with interested Housing Associations. Housing 21 were appointed, along with Aster, Guinness Trust and Hanover.
2.2Housing 21 were awarded £3 million of grant from the Housing Corporation to construct this scheme at Lease Hill, Moredon, and will be borrowing over £3 million privately. The funding package is based on a capital contribution from the Council to construct the day centre and the provision of the land on a long lease at nil consideration. This capital contribution of £300,000 is part of the Council’s approved Capital Programme.
2.3The land is valued at approximately £1.1million and this potential receipt was originally earmarked for improvement works at the Council’s four remaining Residential Care Homes. This requirement was removed as the Council’s budget plans were amended to incorporate the Swindon 2010 promises.
2.4The Borough will have primary nomination rights for the units once completed. The details of the lease will include relevant clauses to secure such nomination rights.
2.5In the case of default on the lease the Borough’s expectations will be included in the lease terms. The assumption will be that should Housing 21 be unable to provide the service, the Borough would source an alternative appropriate provider rather than ‘step in’ and run the scheme itself. Any actions in the event of default would be taken based jointly on the best interests of the residents and ensuring continued best value for the service.
2.6Set out below is further background information on the proposed scheme:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.