Resolved – (1) That the projected outturn for Revenue and the forecast level of General Reserves as at 31st March 2007, be noted. (2) That the additional £328,000 one-off costs of the new Waste Recycling Scheme, and the £18,000 one-off clearance costs for the former Clare’s Site, be noted and funded from the Council’s Corporate Contingency Budget. (3) That, further to the decision in (2) above, and noting paragraph 2.9 of the joint report, the Director of Environment and Health be authorised to issue each household in the Borough with 13 plastic bottle recycling bags per annum, at no charge. (4) That the Revenue Budget virements, detailed in Appendix 3 of the joint report, be approved. (5) That the one-off funding available in 2007/08 as a result of the receipt of additional Local Authority Business Growth Incentive (LABGI) grant and the early transfer of the Revenues and Benefits Service to Capita, be noted. (6) That the Council express its appreciation to [name removed], Director of Customer Services, Revenues and Benefits, and the Revenues and Benefits team, and to the Council’s contractors Liberata, for their hard work, achievements and success in delivering an “excellent” rated Revenues and Benefits Service. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: NM)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member for Resources and Director of Finance Parish / Wards Affected: All Purpose • This report presents the 2007/08 Revenue forecast out-turn at the end of August 2007 including activity data for high-risk budget areas.
Recommendation That Cabinet; • Notes the projected outturn for revenue and the forecast level of General Reserves as at 31st March 2007; • Agrees to fund the additional £328k one-off costs of the new waste recycling scheme, and the £18k one-off clearance costs for the Clare’s site from the Corporate Contingency Budget; • Approves the revenue budget virements detailed in Appendix 3; • Notes the one-off funding available in 2007/08 as a result of the receipt of additional Local Authority Business Growth Incentive (LABGI) grant and the early transfer of the Revenues and Benefits Service to Capita. 1 Reasons 1.1 To update Cabinet on the current forecast position of the Council’s Revenue budgets. 2 Detail Revenue 2.1 The General Fund Revenue forecast outturn for 2007/08 is shown in Table One below with a more detailed analysis shown at Appendix 1. The Council started the financial year with General Reserves of £5 million, being the minimum recommended level. The current projected overspend of £0.728 million would, if realised, reduce the level of General Reserves to £4.272 million which is below the minimum level of £5 million.
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Budget Management 2007/08 - Revenue
Cabinet Date: 31st October 2007
Table One: General Fund Forecast Budget Forecast Forecast Movement 2007/08 Outturn Over/ since last -Underspend month £’000 £’000 £’000 £’000 Children Services 21,650 21,785 135 -201 Housing & Social Care 38,062 38,647 585 0 Environment & Regeneration 24,123 24,219 96 -80 Resources & Leisure 16,871 17,101 230 -20 Business Transformation 11,267 11,267 0 0 Swindon Commercial Services -1,588 -1,588 0 0 Corporate 8,234 7,959 -275 0 Sub Total 118,619 119,390 771 -301 Recharges to Capital -78 0 78 78 Wessex Court Running Costs 121 0 -121 -121 General Contingency Fund 204 204 0 0 Specific Contingencies etc. -1,142 -1,142 0 0 net of one-off funding Total 117,724 118,452 728 -344
2.2Table One above shows that the Council’s budget is projecting to be overspent by £0.728 million by the end of the financial year. A more detailed breakdown of the individual Business Unit budget performance is shown in Appendix 1. The key changes from previously reported figures for each Group Directorate and activity data for key risk areas are set out in Appendix 2. 2.3 Appendix 3 details revenue budget virements that have been requested since the last Cabinet report. Cabinet are asked to approve these new virements. 2.4 A sum of £800k was added to the 2007/08 base budget for the implementation of Single Status part way through the financial year. A further sum of £900k will be added to the base budget in 2008/09. The latest planned implementation date is 1st April 2008 and therefore the £800k budget is unlikely to be needed in 2007/08. However, the uncertainty around the financial impact of Single Status means that there may be a need to carry forward this budget into 2008/09 so at this stage no saving is being anticipated. 2.5 A budget of £221k was added to the 2007/08 budget for the running costs associated with staff moving to Wessex Court. The Wessex Court project is no longer going ahead and therefore there is a saving on this budget. The Wessex Court project was linked to integration savings in Adult Social Care (ASC), which were increased from £250k to £350k on the basis that staff from SBC and
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Budget Management 2007/08 - Revenue
Cabinet Date: 31st October 2007
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.