Draft Capital Programme Proposals 2007/2008 to 2010/11

Agreed Executive 2 papers

Cabinet agreed this item on Wednesday 12 December 2007. Below is the council's own wording, with the papers it was decided on.

Item101

Resolved

Resolved – (1) That the initial results of the refresh of the Capital Programme for 2007/08 to 2009/10, previously agreed by the Council, updating the spending profile to reflect latest estimates, be noted and endorsed. (2) That proposals for new capital expenditure be developed within the broad themes set out in paragraph 2.8 of the joint report. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: RB)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet, 12 pages

Appendix One Group Re-profiling and Changes 2007/08 to 2009/10

Capital Programme Expenditure Group Directorate Original Refresh Variance Original Refresh Variance Original Refresh Variance # Refresh Original Refresh Variance 2007/08 2007/08 2007/08 2008/09 2008/09 2008/09 2009/10 2009/10 2009/10 2010/11 + Total Total Total £m £m £m £m £m £m £m £m £m £m £m £m £m Children's 40.390 20.991 -19.399 39.681 29.368 -10.312 18.290 19.311 1.021 4.000 98.360 73.670 -24.690 Environment and Regeneration 19.886 16.810 -3.076 9.730 9.644 -0.086 8.121 7.880 -0.240 1.586 37.737 35.921 -1.816 Housing and Social Care 17.739 14.718 -3.020 14.409 14.676 0.268 11.268 13.500 2.232 1.070 43.415 43.965 0.550 Resources & Leisure 18.468 15.816 -2.652 4.831 6.222 1.391 2.806 3.607 0.801 0.225 26.105 25.871 -0.235 Swindon Commercial Services 0.076 0.058 -0.018 0.062 0.080 0.018 0.000 0.000 0.000 0.000 0.138 0.138 0.000 Business Transformation 9.659 9.273 -0.386 0.822 0.003 -0.819 0.535 0.000 -0.535 0.000 11.016 9.276 -1.740 Corporate 1.887 4.484 2.597 0.384 0.500 0.116 0.394 0.500 0.106 0.000 2.665 5.484 2.819 Wichelstowe 0.099 0.399 0.300 0.200 0.710 0.510 0.150 0.320 0.170 0.000 0.449 1.429 0.980 Total 108.204 82.549 -25.655 70.117 61.203 -8.914 41.563 45.119 3.555 6.882 219.885 195.753 -24.132

Capital Programme Assumed Funding Original Refresh Variance Original Refresh Variance Original Refresh Variance Refresh Original Refresh Variance 2007/08 2007/08 2007/08 2008/09 2008/09 2008/09 2009/10 2009/10 2009/10 2010/11 + Total Total Total £m £m £m £m £m £m £m £m £m £m £m £m £m External Grant 46.387 31.129 -15.259 33.927 22.618 -11.310 17.953 14.463 -3.490 3.600 98.268 71.810 -26.459 Section 106 0.966 0.794 -0.172 0.570 0.320 -0.250 0.750 0.500 -0.250 0.000 2.286 1.614 -0.672 Capital Receipt 4.001 2.441 -1.560 9.210 8.380 -0.829 7.400 8.700 1.300 1.000 20.610 20.521 -0.090 Revenue 0.535 0.542 0.007 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.535 0.542 0.007 CCR - Prudential Borrowing 10.688 11.008 0.320 0.697 0.805 0.108 0.035 0.000 -0.035 0.000 11.420 11.813 0.393 CCR - Borrowing 13.000 13.000 0.000 13.000 13.000 0.000 13.000 13.000 0.000 0.000 39.000 39.000 0.000 CCR - Borrowing c/f 10.120 10.120 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 10.120 10.120 0.000 CCR - Capital Receipts 22.507 12.060 -10.447 12.713 19.020 6.307 2.425 11.000 8.575 2.282 37.645 44.361 6.716 Shortfall / Surplus (-) in Receipts 0.000 1.457 1.457 0.000 -2.939 -2.939 0.000 -2.545 -2.545 0.000 0.000 -4.028 0.000 Total 108.204 82.549 -25.655 70.117 61.203 -8.914 41.563 45.119 3.555 6.882 219.885 195.753 -24.132

Cumulative shortfall / surplus (-) in Receipts 1.457 -1.483 -4.028 -0.746 -0.746

Memorandum Item: Academy (11- 19 yr old element) 12.500 12.400 3.200 28.100 Total including Academy (11-19) 95.049 73.603 48.319 223.853

As part of the refresh of the Capital Programme, the 11 – 19 year old element of the Academy has been removed and will be monitored separately as a memorandum item. While this scheme does represent a significant element of capital expenditure, it does not have an impact upon Swindon Borough Council funding nor does it generate an asset for the Council. # Refresh 2010/11+ column only includes those schemes that have already been agreed in the original programme Appendix 2 - Detailed Capital Programme Proposals 2007 - 2010 By Group Children Refresh Refresh Refresh Refresh Refresh Total - Refresh Funding

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Draft Capital Programme Proposals: Appendices: 1 and 2: Summary and Capital Programme by ServiceReport 12 pages DownloadRead as text
PDF
Draft Capital Programme Proposals 2007/2008 to 2010/11Report 5 pages Download

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. Draft Capital Programme Proposals 2007/2008 to 2010/11This decision
  2. Capital Programme 2026/2027 (Minute for Confirmation)Approved
  3. Capital Programme 2025-2026Approved
  4. Capital Programme 2024/2025 (Minute for Confirmation)Approved
  5. Capital programme 2023-24 (Minute for Confirmation)Approved
  6. Capital Programme to 2026/27 (Minute for Confirmation)Approved

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies