New Primary School on PS7 Site, Oakhurst, Swindon - Proposed Procurement Route

Decided Executive 1 paper

Cabinet decided this item on Wednesday 11 June 2008. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

Resolved – (1) That the construction of the new primary school at Oakhurst, Swindon, on the PS7 site, together with the proposed temporary arrangements for that school, be included in the Swindon Commercial Services extended “Core Basket” of work. (2) That, in order to enable the decision in (1) above to be implemented, the Council’s Contract Standing Orders be waived to allow Swindon Commercial Services to undertake this work, without the requirement for external tendering, for the reasons set out in this joint report. (3) That Swindon Commercial Services’ Commissioning Board, in conjunction with the Client for this project, Children Services, be required to demonstrate to the Cabinet that value for money is being delivered for this project and a system of “open book” accounting is in operation. (4) That the Chief Executive, in consultation with the relevant Cabinet Members, be authorised to include other appropriate works within the Swindon Commercial Services extended “Core Basket” of work. The reasons for the decision and alternative options are as set out in the reports to the meeting. (CM: DR)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet, 7 pages

Background

2.1As indicated above, the Cabinet has recently agreed that a new primary school is constructed on the PS7 site and that temporary accommodation, if possible, is provided in advance of that to address the increasing primary pupil population in the Northern Sector.

2.2There is a clear aim to open the new all-through primary school by September 2010, with temporary accommodation potentially for Reception and Year 1 pupils in place for September 2009. A Project Board, involving all key stakeholders, including Capita, has been established by the Client and initial design and survey work of the site has commenced.

2.3It was reported to the February Cabinet meeting that the estimated cost of the permanent building was up to £7m and that the estimated cost of the temporary facility was up to £0.75m.

Swindon Commercial Services – “Core Basket” of Work

2.4Following the decision of the Cabinet on 7 June 2006 that SCS should be established as the Council’s in-house “strategic partner”, a number of capital projects from across the Council were included within a “Core Basket” of work. A key consideration for the Cabinet was to ensure that a service performance framework was introduced, with clear evidence of benchmarking, to secure value for money for the programme of work.

2.5At that time, a number of Children Services capital projects were incorporated within the “Core Basket”, including the rebuilding of three primary schools in West Swindon, at Shaw Ridge, Millbrook and Toothill.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New Primary School on PS7 Site, Oakhurst, Swindon: Proposed Procurement RouteReport 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. New Primary School on PS7 Site, Oakhurst, Swindon - Proposed Procurement RouteThis decision
  2. New Primary School and Secondary School Place Planning ConsultationAgreed
  3. Competition Arrangements for Proposed New Primary School at Croft, Old Town, SwindonNoted
  4. Proposed New Primary School at Croft, Old Town, Swindon - Competition ArrangementsNoted
  5. Competition Arrangements for Proposed New Croft Primary SchoolApproved
  6. New Primary School at the PS7 Site, Northern Sector, Swindon - Competition ArrangementsNoted

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies