Resolved – (1) That the current projected outturn for Revenue, as set out in Table 1 to the joint report, and the forecast level of General Reserves as at 31 st March 2009, be noted. (2) That the action being taken to bring the Council’s Revenue Budget for 2008/09 in on target, be noted. (3) That the Chief Executive be authorised to allocate up to £250,000 on business cases, as part of the new “Gavin’s Den” initiative and endorses the first initiative of £25,000, as referred to in paragraphs 2.8 to 2.10 of the joint report. (4) That the Revenue Budget virements set out in Appendix 4 to the joint report, be approved. (5) That the Director of Finance be authorised to release £50,000 from the Council’s Regeneration Reserve towards the Mechanics Institute project, as referred to in paragraphs 2.11 and 2.12 of the joint report. The reasons for the decision and any alternative options considered are as set out in the report to the meeting. (CM: PG / PY)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member for Resources and Director of Finance
Purpose • This report presents the 2008/09 Revenue forecast out-turn at the end of November 2008 including activity data for high-risk Budget areas.
Recommendation That Cabinet: • Notes the current projected outturn for revenue as set out in Table 1 and the forecast level of General Reserves as at 31st March 2009; • Notes the action being taken to bring the Council’s budget in on target; • Grants the Chief Executive authority to allocate up to £250k on business cases as part of the new “Gavin’s Den” initiative and endorses the first initiative of £25k; • Agrees the revenue virements set out in Appendix 4; • Agrees to release £50k from the Council’s Regeneration Reserve towards the Mechanics Institute project.
1 Reasons General Fund Revenue Account 1.1 To update Cabinet on the current forecast position of the Council’s Revenue Budgets. The forecasts are based on data as at the end of November 2008. 2 Detail 2.1 An overspend of £0.921m against the approved budget of £123.478m was predicted when the 2008/09 revenue budget position was last reported to Cabinet at its December meeting. Since those figures, Corporate Board has been updated with on-going updates, which showed indications that the economic downturn was continuing to have a major impact on delivery of the budget. 2.2 The General Fund revenue forecast outturn for 2008/09 based on the November monitoring is shown in Table 1 below with a more detailed analysis shown at Appendix 1. This includes the savings expected from the non-essential expenditure freeze put in place by Corporate Board and endorsed by Cabinet in December. 2.3 Appendix 3 contains more detailed listing of the actions that have been put in place to mitigate non-essential expenditure. However, a number of new cost pressures have arisen since the last report and therefore the improvement is only shown as £427k in Table 1 below.
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Revenue Budget Management 2008/09
Cabinet Date: 21st January 2009
Table 1: General Fund Forecast Budget Forecast Forecast Movement 2008/09 Outturn Over/ Since Underspend December Cabinet £’000 £’000 £’000 £’000 Children Services 27,772 28,015 243 -35 Housing & Social Care 49,972 51,239 1,267 157 Environment & 28,856 28,986 130 -447 Regeneration Business Transformation 16,411 16,628 217 264 Swindon Commercial -1,460 -1,443 17 -2 Services Chief Executive & 1,581 201 -1,380 -364 Corporate Sub Total 123,132 123,626 494 -427 Contingency Fund 346 346 0 0 Total 123,478 123,972 494 -427
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.