Resolved – That, subject to the confirmation of the Council: (a) The projected outturn for the Capital Programme for 2008/09, be noted. (b) The Council’s refreshed Capital Programme for the period 2008/09 to 2010/11, as summarised in Table 4 and detailed in Appendix 2 to the joint report, and including the changes proposed in paragraphs 2.13 and 2.14 of the joint report, be approved. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: ME)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member for Resources and Director of Finance
Purpose • This report presents the Council’s current 3-year Capital programme, including the forecast 2008/09-outturn position. •
Recommendation That Cabinet • Notes the projected 2008/09 outturn of the Capital Programme; • • Approves the refreshed Capital Programme 2008/09 – 2010/11 as summarised in Table 4 and detailed in Appendix 2, including the changes proposed in paragraphs 2.13 and 2.14. • . 1 Reasons 1.1 To update Cabinet on the current projected 2008/09 outturn position of the Council’s Capital programme. The forecasts are based on data as at the end of December 2008. 1.2 To present a summary of the Council’s current 3 year Capital Programme including sources of funding.
2 Detail Capital Programme 2008/09 2.1 The capital programme for 2008/09 is summarised in table 1 below. This includes expenditure on Wichelstowe, which is currently funded through the Collaboration Account agreement, as well as an estimate of expenditure funded through S.106 receipts. 2.2 The figures in Table 1 include the additions to the Capital Programme approved by Cabinet in December plus the following changes that are all grant funded: o an increase of £259k New Growth Points funding originally budgeted in 09/10 but now to be received in 08/09 o an increase of £240k Home Zone funding due to favourable exchange rate fluctuations o a reduction in Adult Social Care ICT grant of £48k from that originally estimated
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No. 463967 or Email [email protected] Capital Programme Update 2008/09 - 2010/11
Cabinet Date: 11th February 2009
Table 1: Capital Expenditure and Forecasts 2008/09 Group 2008/09 Current Projected Profiled Actual to Variance Budget Forecast Variance Budget Date to Date to Date
£’000 s £’000 s £’000 s £’000 s £’000 s £’000 s Children's 32,187 24,109 (8,078) 19,002 8,611 (10,391) Services Environment & 12,639 12,626 (13) 5,988 4,481 (1,507) Regeneration Housing & 21,572 18,481 (3,091) 15,953 10,052 (5,901) Social Care Business 5,510 4,562 (948) 3,456 1,868 (1,588) Transformation S.C.S. 105 105 - 85 - (85) Strategic 3,365 3,352 (13) 2,403 1200 (1,203) Partnership Service Totals 75,378 63,235 (12,143) 46,887 26,212 (20,675)
Wichelstowe 7,856 7,856 - 5,892 4,616 (1,276)
S106 Schemes 6,030 6,030 - 4,522 4,105 (417) Grand Totals 89,264 77,121 (12,143) 57,301 34,933 (22,368) 2.3 Table 2 below, gives a breakdown of the projected variance by service area: Table 2 Analysis of Projected Variance by Service Area. Potential Potential Accelerated Savings Overspend In-Year In-Year Projected Group 08/09 08/09 Spend Slippage Variance £'000s £'000s £'000s £'000s £'000s Children’s (305) 143 180 (8,096) (8,078) Services Environment & (339) 10 1,186 (870) (13) Regeneration Housing & (811) 161 - (2,441) (3,091) Social Care Business (2) 4 (950) (948) Transformation Strategic (13) (13) Partnership Totals (1,470) 318 1,366 (12,357) (12,143) 2.4 The accelerated in-year spend column in table 2 refers to those schemes which are spending more than anticipated in 2008/09 but within total budget overall.
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No. 463967 or Email [email protected] Capital Programme Update 2008/09 - 2010/11
Cabinet Date: 11th February 2009
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.