CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swindon Borough Council
Cabinet, Wednesday 9 September 2009

Capital Programme Monitoring

Approved Executive 5 papers

Cabinet approved this item on Wednesday 9 September 2009. Below is the council's own wording, with the papers it was decided on.

Item38

Resolved

Resolved – (1) That the proposed additions and amendments to the Capital Programme, as detailed in paragraphs 2.11 to 2.20 of the joint report, be endorsed, and the refreshed Capital Programme, as detailed in Appendix 1, be approved. (2) That the projected 2009/10 Capital Programme Outturn position and the sources of funding available to the Council, be noted. (3) That the revised processes for Section106 Agreement financial monitoring, as described in paragraphs 2.25 to 2.27 of the joint report, be noted and endorsed. (4) That the Council’s Treasury Management performance to June 2009, as referred to in the joint report, be noted The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: DR)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet, 10 pages

Capital Programme Monitoring

Cabinet Date: 9 September 2009

Author: Cabinet Member for Finance and Benefits and Director of Finance

Purpose  This report presents the Council’s current 3-year Capital programme, the forecast 2009/10-outturn position and funding position, and the Treasury Management performance for the first quarter. 

Recommendation That Cabinet:  Approves the additions and amendments to the programme detailed at paragraphs 2.11 to 2.20 and approves the refreshed Capital Programme detailed in Appendix 1.  Notes the projected 2009/10 Capital Out-turn position and the sources of funding.  Notes the revised processes for S.106 financial monitoring as described in paragraphs 2.25 – 2.27.  Notes the Treasury Management performance to June 2009.  1 Reasons 1.1 To update Cabinet on the current projected 2009/10 Capital Programme Out-turn position. The forecasts are based on data as at the end of July 2009. 1.2 To present a summary of the Council’s current 3 year Capital Programme including sources of funding. 2 Detail Capital Programme Refresh 2.1 During July officers have undertaken a review of the current Capital Programme. The Capital team has worked with service areas and individual Project Managers to review and, where appropriate, re-profile capital programme budgets between financial years so that they better match when expenditure is projected to occur. In addition to re-profiling, officers have identified savings on completed schemes and on budgets no longer required of circa £1.8m (after covering several minor overspends). These savings have been reflected in the refreshed capital programme.

Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No. 463976 or Email [email protected] Capital Programme Monitoring

Cabinet Date: 9 September 2009

2.2A scheme-by-scheme breakdown of Capital Programme budgets can be found at Appendix 1. Full details of all savings taken and overspends covered are available in Appendix 2. Housing Revenue Account (HRA) Capital spend is treated as a single scheme for Capital Programming purposes, and there is only one SCS scheme (Replacement of LPG Vehicles) therefore there is no breakdown for these areas in Appendix 1. Capital Programme 2009/10 2.3 The capital programme for 2009/10 is summarised in table 1 below, assuming that the changes detailed in the report and its appendices are accepted by Cabinet. Table 1: Capital Expenditure and Forecasts 2009/10

2009/10 Current Projected Budget Actual Variance Group Budget Forecast Variance to date to Date to Date £'000 £'000 £'000 £'000 £'000 £'000 Children's Services 42,133 42,290 158 14,044 4,249 (9,795) Environment & Regeneration 18,459 18,459 0 6,153 1,158 (4,995) Housing & Social Care 2,795 2,851 57 932 (138) (1,069) Housing Revenue Account 10,253 10,253 0 3,418 485 (2,932) Business Transformation & 23,883 33,074 9,190 7,961 8,615 654 Corp. Swindon Commercial 38 38 0 13 0 (13) Services Strategic Partnership 3,068 3,068 0 1,023 855 (167) Service Totals 100,628 110,033 9,405 33,543 15,225 (18,317) 100% S.106 funded schemes 2,950 2,950 0 983 466 (517) Grand Totals 103,578 112,983 9,405 34,526 15,691 (18,834)

2.4Table 2 below, gives a breakdown of the projected variance by service area Forecast Potential Potential Accelerated Forecast Total Group Savings Overspends Expenditure Slippage variance £'000 £'000 £'000 £'000 £'000 Children's Services 0 158 0 0 158 Environment & Regeneration 0 0 0 0 0 Housing & Social Care 0 57 0 0 57 Housing Revenue Account 0 0 0 0 0 Business Transformation & 0 9,190 0 0 9,190 Corp. Swindon Commercial Services 0 0 0 0 0

Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No. 463976 or Email [email protected] Capital Programme Monitoring

Cabinet Date: 9 September 2009

Strategic Partnership 0 0 0 0 0 Totals 0 9,405 0 0 9,405

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Directorate and Scheme Refreshed Capital ProgrammeAppendix 1 7 pages Download
PDF
VariationsAppendix 2 1 pages Download
PDF
Section 106 Funded ExpenditureAppendix 3 2 pages Download
PDF
Investments: June 2009Appendix 4 1 pages Download
PDF
Capital Programme MonitoringReport 10 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. Capital Programme MonitoringThis decision
  2. Capital Programme 2026/2027 (Minute for Confirmation)Approved
  3. Capital Programme 2025-2026Approved
  4. Capital Programme 2024/2025 (Minute for Confirmation)Approved
  5. Capital programme 2023-24 (Minute for Confirmation)Approved
  6. Capital Programme to 2026/27 (Minute for Confirmation)Approved

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies