Resolved - (1) That the protocol for dealing with minor amendments outlined in the report be adopted subject to the following addition: That in cases where an amendment is requested in relation to an application granted by the Planning Committee, Ward Members will be notified of the request. If members wish to clarify any matters they should do so with the case officer within 7 working days of the date of the notification. (2) That the protocol be made publicly available and published on the councils website
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
That the Planning Committee agrees that: The protocol for dealing with minor amendments outlined in this report be adopted. The protocol be made available and published on the councils website
1. Reasons
1.1The process and procedures for the determination of planning and related applications are under constant review in order to improve the standards of performance.
1.2The Planning Act 2008 (section 190) has provides planning authorities with statutory power to make changes to planning permissions where such changes are considered to be non-material. The introduction of this statutory provision formalises a procedure already adopted by the Council and a number of other planning authorities, which allows minor amendments to be made to planning permissions, and gives an opportunity to establish the procedures by which applications for minor amendments are dealt with.
2. Detail
Background
2.1The role of the Planning Department extends either side of the 8 or 13 week planning application period, both pre-application and post-application discussions represent a significant proportion of Planning case load and are essential to the successful implementation of development.
Further information on the subject of this report can be obtained from Nicola Rogers on 466517 or Email [email protected]. New Non- Material Amendments Protocol Planning Committee 10 November 2009
2.2The Town and Country Planning (General Development Procedure) (Amendment No.3) (England) Order 2009 introduced the provision on 1st October 2009 for making non-material changes to planning permission. This results in the ability to make a change to a planning permission that has been granted without having to make a full application again. Many Local Planning Authorities have, in the past, offered an informal minor amendment procedure, but the recent Act and subsequent secondary legislation formalise this process.
2.3The new procedure requires an application for an amendment to be made on a standard form and a fee will be payable (currently free but fees are expected to be introduced in November). No provision is made for consultation as the changes are expected to be so minor that they will have no further adverse impact. As with a planning application, a certificate of ownership is required to be completed and the site owner informed. Decisions must be made within 28 days.
2.4The amended legislation does not give detailed advice as to what an LPA might consider to be a ‘non-material’ amendment, therefore an Authority’s procedures regarding all forms of non-material amendment should be clearly laid down in a procedure note, which has been adopted and published and which is widely available to members of the public, agents and developers. This will help ensure consistency between officers, create transparency and help prevent complaints of inconsistency about the service.
Approach
2.5Whilst developers and agents generally favour an amendment procedure as a helpful method of dealing with unexpected changes in circumstances or site conditions when a development is underway, it is regarded less favourably by those who are denied the ability to participate in the process, such as Parish Councils or neighbours. It is therefore essential that the amenities and needs of those affected by the proposed changes be considered when determining a non-material amendment.
2.6There is also a need to be alert to the potential danger of cumulative or incremental changes to approved schemes which can arise from a succession of non-material amendments, resulting in a substantial departure from what was originally approved.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Speaking at Planning CommitteeResolved – To approve the changes to the public speaking protocol as outlined in the report and in the attached docum...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.