Resolved – (1) That the current projected out-turn, as set out in Table 1, and the emerging issues set out in the body of the joint report, be noted. (2) That the worsening positioning within the Housing and Social Care Budget, and how this impacts on that Group’s ability to balance future year’s cash limits, be noted. (3) That the actions taken by the Group Director, Housing and Social Care to address the overspend within that Group, be recognised. (4) That the Revenue virements, set out in Appendix 2 to the joint report, be approved. The reasons for the decision and any alternative options considered are as set out in the report to the meeting.
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member for Finance and Benefits and Director of Finance
Purpose This report presents the 2009/10 Revenue forecast out-turn at the end of October 2009.
Recommendation That Cabinet: Notes the current projected outturn set out in Table 1 and the emerging issues set out in the body of the report; Considers the worsening positioning within Housing and Social Care and how this impacts on that Group’s ability to balance future year’s cash limits. Notes the actions by the Group Director of Housing & Social Care to address the overspend. Approves the virements in Appendix 2
1 Reasons General Fund Revenue Account 1.1 To update Cabinet on the current forecast position of the Council’s Revenue Budgets. The forecasts are based on data as at the end of October 2009. 2 Detail 2.1 The General Fund revenue forecast outturn for 2009/10 based on the October monitoring data is shown in Table 1 below with a more detailed analysis shown at Appendix 1. The current projected outturn, before the impact of further mitigating actions, is an overall forecast overspend of £1.327m, against which £0.757m remains unallocated in the general contingency fund. Pressures from increasing costs and reducing income levels are resulting in Group projected overspends (subject to the further impact of management actions) of £3.770m, partly offset by forecast savings on debt charges and a predicted excess dividend in SCS. 2.2 The further increase in the projected overspend compared with last month is as a result of continued increasing demand in Adult Social Care. Overview 2.3 It is encouraging that management actions being taken by Groups are continuing to identify savings to offset the reported overspends. However, new pressures in Adult Social Care have resulted in a net increase in the projected out-turn for that Group after mitigating actions. Adult Social Care is projecting a £2.3m overspend and Cabinet needs to also consider this in the context of the 2010/11 Budget.
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Revenue Budget Management 2009/10
Cabinet Date: 9th December 2009
2.4The impact of the non-essential expenditure freeze is beginning to be seen in Group projections but, unfortunately new unbudgeted costs are continuing to put pressure on the Council-wide projected out-turn. Table 1: General Fund Forecast Budget Forecast Forecast Movement 2009/10 Outturn Over/ Since Underspend September Cabinet £’000 £’000 £’000 £’000 Children Services 28,139 28,834 695 -141 Housing & Social 46,451 48,772 2,321 805 Care Environment & 31,762 31,991 229 -239 Regeneration Business 18,240 18,765 525 -75 Transformation Sub Total of Group 124,592 128,362 3,770 350 Position Swindon Commercial -2,006 -2,129 -123 83 Services Chief Executive & 4,474 3,643 -831 18 Corporate Sub Total 127,060 129,856 2,816 451 General Contingency 2,246 757 -1,489 0 Fund Total 129,306 130,613 1,327 451
3 Group Directorate Summaries Children Services 3.1 There has been an improvement in the current revenue position within Children Services. The forecast is still an overspend position, however it has reduced by a further £141k to £695k. 3.2 The key risks within Children Services continue to be the demand led budgets including residential, independent and in-house care provision for vulnerable children and young people. The leadership team continually look at possible areas of the budget that may help to reduce the over spend and have re-prioritised grant funded services as well as placing a freeze on non- essential expenditure and recruitment that has contributed to the improved position over the last four months. 3.3 The net position for the Group is summarised below:- o Undelivered Savings - £0.276m o New Pressures in 2009/10 - £0.713m o Less Management Actions – (£0.294m) o Net projected overspend - £0.695m
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.