Resolved – (1) That the small-scale, modular, waste treatment solution, as set out in Option D, be approved and adopted as the Strategy for the management of Non-Recyclable Municipal Waste in Swindon. (2) That the identified capital requirement in Option D of £8.3M, plus procurement costs of £300,000, be included within the current consultation on the Council’s 4-year Capital Programme 2010/11 to 2013/14, noting the availability of the Waste Infrastructure Capital Grant, and recognising the Strategy’s importance in mitigating future revenue cost pressures for the Council. (3) That the Deputy Chief Executive and Group Director, Environment, Regeneration and Community be requested to thank Wiltshire Council for the joint working which has helped formulate this Council’s proposed Strategy. (4) That, subject to the necessary funding availability, the Deputy Chief Executive and Group Director, Environment, Regeneration and Community, in consultation with the Deputy Leader ... view the full minutes text for item 88. (CM: GP)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Waste Management Strategy – Towards Zero Waste To Landfill CABINET Date: 20 January 2010
Authors: Deputy Leader of the Council Cabinet Member for Sustainability, Transport & Strategic Planning Deputy Chief Executive Parish / Wards Affected: All
Purpose To ask Cabinet to approve the proposed strategy for the management of the Borough’s non-recyclable Municipal Waste.
Recommendation Cabinet is requested to Approve the small-scale, modular, waste treatment solution as set out in Option D as the Strategy for the management of non-recyclable Municipal Waste in Swindon; Include the identified capital requirement in Option D of £8.3M, plus procurement costs of £300k, within the current consultation on the Council’s 4-year Capital Programme 2010/11 to 2013/14, noting the availability of the Waste Infrastructure Capital Grant, and recognising the Strategy’s importance in mitigating future revenue cost pressures for the Council; Request the Deputy Chief Executive and Group Director of Environment, Regeneration and Communities to thank Wiltshire Council for the joint working which has helped formulate this Council’s proposed Strategy; Subject to the necessary funding availability, to authorise the Deputy Chief Executive and Group Director of Environment, Regeneration and Communities, in consultation with the Deputy Leader of the Council and the Cabinet Member for Sustainability, Transport and Strategic Planning, to progress Option D, in compliance with the Council’s Gateway Procurement Process; Note that until alternative arrangements are put in place, waste collection and disposal under the Strategy will be delivered by Swindon Commercial Services Limited as part of the Core Basket previously approved by Cabinet; Authorise the Director of Law and Democratic Services to: o seek such external Legal advice as is necessary, and o enter into the necessary documentation to procure the project, in consultation with the Deputy Chief Executive and Group Director of Environment, Regeneration and Communities and the Deputy Leader of the Council and Cabinet Member for Sustainability, Transport and Strategic Planning, on such terms and conditions as are necessary to protect the Council’s interests.
Further information on the subject of this report can be obtained from Richard Fisher on 466461 or Email [email protected] Waste Management Strategy – Towards Zero Waste To Landfill CABINET Date: 20 January 2010
1. Reasons 1.1 Swindon Borough Council needs to address the management of the Borough’s Municipal Solid Waste (MSW) in order to meet the requirement to reduce the quantity of waste sent to landfill, and its adopted One Planet Living objectives.
1.2A joint study by Wiltshire Council and Swindon Borough Council (SBC) has been completed to identify the viability of a joint solution to address these requirements. The study has concluded that a joint solution would not satisfy our need within the required timescales.
1.3A potential solution has been identified and is proposed to be adopted by SBC as its way forward.
2 Detail
2.1SBC, in its role as Waste Disposal Authority, must reduce the amount of waste it sends to landfill. Whilst small amounts of trading between authorities can take place, the Council needs to adopt a Strategy that reduces waste to landfill to avoid financial penalties and possible prosecution. The financial penalties are managed through the Landfill Allowances and Trading Scheme (LATS) and the latest projection of penalty levels is shown in Appendix 1.
2.2Furthermore, the Council has adopted the One Planet Living framework for sustainability and ‘Zero Waste’ is Principle 2 of this framework. A solution for One Planet Living: Zero Waste will satisfy the requirements of the allowances scheme. Zero waste to landfill refers to the biodegradable element of the waste. Marginal quantities of certain types of waste may be landfilled whilst alternative technologies are developed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.