Resolved – That the conditional date referring to planning permission to be granted in order to permanently expand St Francis Church of England Primary School, Taw Hill, Swindon, be modified from 31 st March 2010 to 31 st August 2010, for the reasons set out in the joint report. (CM: GP)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
The Permanent Expansion of St Francis Church of England Primary School CABINET PANEL Date: 3rd February 2010
Author: Cabinet Member for Children’s Services and Group Director, Children
Parish / Wards Affected: Abbey Meads
Purpose To modify the date of conditions as set out in the decision to expand St Francis Church of England Primary School.
Recommendation The Cabinet Panel is requested to Modify the conditional date referring to planning permission to be granted in order to permanently expand St Francis Church of England Primary School.
1. Reasons 1.1 The aim of the permanent expansion is to provide sufficient classroom space at St Francis Church of England Primary School to sustain a long- term increase in admission numbers.
2. Detail 2.1 At its meeting of 8th July 2009 the Cabinet Panel approved the proposal to permanently expand St Francis Church of England Primary School by one form of entry.
2.2The decision was subject to the following condition: that the granting of Planning Permission and agreement with the Developers for the change of use of relevant parts of the land to enable the extension of the current building being achieved by 31st March 2010. A copy of the agreed minute of the meeting is attached as Appendix 1.
2.3Negotiations have been taking place between Swindon Borough Council and Taylor Wimpey (the developers) for the change of use of relevant parts of the site. Agreement between both parties was secured in principle on 17th December 2009.
2.4The agreement will allow the expansion of the school to proceed. However, a modification to the original date of the condition is sought to a later date of 31st December 2010 to enable the proposed extension to proceed through the planning process.
Further information on the subject of this report can be obtained from Ian Bickerton, Director Access and Provision on 465724 or Email [email protected]. The Permanent Expansion of St Francis Church of England Primary School CABINET PANEL Date: 3rd February 2010
Alternative Options o If a modification is not granted there will not be adequate time for the proposed extension to proceed through the planning process. If a condition is not met by the date specified, the proposals should be referred back to the decision maker for fresh consideration. o If additional places are not provided in North Swindon there will be a shortfall and this will have an impact on parental preference and rise in the number of appeals.
Risk Management Financial and Procurement Implications There are no direct financial or procurement implications as a result of this report
Legal / Human Rights Implications The Cabinet must follow Department for Children, Schools and Families Guidance entitled "Decision Makers Guidance for Expanding a Maintained Mainstream School”.
The Guidance states that the decision maker (Cabinet Panel) must set a date by which the condition should be met, but will be able to modify the date if proposers confirm, before the date expires, that the condition will be met later than originally thought.
Links to Corporate Plans and Policies (in particular to Swindon 2010 Promises) There is a link to the Strategic Management Plan for Children Services and the proposed expansion would support Council Promises 20 and 45. The scheme links to Theme 1 Swindon’s young people have high aspirations and are consistently achieving well.
Consultees The Director of Finance (Section 151 Officer) and Director of Law and Democratic Services (Monitoring Officer) are consulted in respect of all reports. Background Papers and Appendices Appendix 1 – Copy of the Cabinet Panel Minutes dated 8th July 2009
Further information on the subject of this report can be obtained from Ian Bickerton, Director Access and Provision on 465724 or Email [email protected].
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.