Resolved – That, subject to the confirmation of the Council: (a) The projected outturn for the Capital Programme for 2009/10, be noted, and the proposed additions to the current year’s Capital Programme, as detailed in paragraphs 2.9 and 2.10 of the joint report, be approved. (b) It be noted that capital expenditure of £57m is currently approved for 2010/11, as detailed in Appendix 1 to the joint report, which may increase if planned expenditure in the current year is delayed into next year. (c) The list of new capital schemes, as set out in Appendix 2 to the joint report, be approved to commence in 2010/11 (d) The capital schemes, detailed in Appendix 3 to the joint report, be considered as priorities for inclusion in the Capital Programme in future years, subject to funding being available. (e) Feasibility studies be completed for all capital schemes with an estimated cost in excess of £0.5m. (f) The Cabinet Member for Finance and Benefits, in consultation with the relevant Cabinet Member, be authorized to approve for inclusion in the Capital Programme any new scheme that is within the Council’s Budget and Policy framework that supports the Council’s objectives, and is to be fully funded by external resources The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: ME)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Director of Finance and Cabinet Member for Finance and Benefits
Purpose This report presents the latest position on delivery and funding of the Council’s current approved Capital Programme and proposals for new capital schemes from 2010/11.
Recommendation That Cabinet: Approves the proposed additions to the current year’s capital programme detailed in paragraphs 2.9 and 2.10; Notes that capital expenditure of £57m is currently approved for 2010/11 as detailed in Appendix 1, which may increase if planned expenditure in the current year is delayed into next year; Recommends to Council that the list of new schemes shown in Appendix 2 be approved to commence in 2010/11; Recommends to Council that the schemes detailed in Appendix 3 be considered as priorities for inclusion in the Capital Programme in future years, subject to funding being available; Recommends that feasibility studies be completed on all schemes with an estimated cost in excess of £0.5m. The Cabinet Member for Finance and Benefits, in consultation with the relevant Cabinet Member be authorised to approve for inclusion in the Capital Programme any new scheme that is within the Council's Budget and Policy framework that supports the Council's objectives, and is to be fully funded by external resources.
1 Reasons 1.1 To update the Cabinet on the current projected 2009/10 Capital Programme Out-turn position. The forecasts are based on data as at the end of December 2009. 1.2 To present a summary of the Council’s current 3 year Capital Programme, including sources of funding, and proposals for the future Capital Programme. 2 Detail Capital Programme 2009/10 2.1 The Capital Programme for 2009/10 is summarised in table 1 below.
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No. 463976 or Email [email protected] Capital Programme 2009/10 to 2013/14
Cabinet Date: 10 February 2010
Table 1: Capital Expenditure and Forecasts 2009/10
2009/10 Current Projected Budget Actual Variance Group Budget Forecast Variance to date to Date to Date £'000 £'000 £'000 £'000 £'000 £'000 Children's Services 44,858 39,793 (5,065) 33,643 23,980 (9,664) Environment & Regeneration 22,509 18,168 (4,341) 16,882 6,551 (10,331) Adult Social Care & Leisure 2,950 2,918 (32) 2,212 804 (1,409) Housing Revenue Account 10,253 10,253 0 7,690 3,941 (3,749) Business Transformation & 27,377 35,803 8,426 20,533 16,447 (4,085) Corp. Swindon Commercial Services 38 38 0 28 0 (28) Strategic Partnership 1,062 1,062 (1) 797 478 (318) Service Totals 109,047 108,035 (1,012) 81,785 52,200 (29,585)
2.2Table 2 below, gives a breakdown of the projected variance by service area: Table 2: Variance by Service Area Forecast Potential Potential Accelerated Forecast Total Group Savings Overspends Expenditure Rephasing variance £'000 £'000 £'000 £'000 £'000 Children's Services (1,500) 89 163 (3,817) (5,065) Environment & Regeneration (650) 93 0 (3,784) (4,341) Adult Social Care & Leisure (26) 382 0 (389) (32) Housing Revenue Account 0 0 0 0 0 Business Transformation & 0 8,866 0 (440) 8,426 Corp. Swindon Commercial Services 0 0 0 0 0 Strategic Partnership (1) 0 0 0 (1) Totals (2,177) 9,430 163 (8,430) (1,012)
Details of Projected Variance 2.3 The projected variance of (£5.1m) in Children’s services is made up of: £1.5m of potential savings relating to school buildings projects £3.8m of forecast rephasing which relates to: o £2.5m Devolved Formula Capital o £580k Greendown ASD Unit o £445k Extended Schools Phase 3 o £150k Parking at Crowdys School o £125k other £89k potential overspends relating to: o £33k the Academy project
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No. 463976 or Email [email protected] Capital Programme 2009/10 to 2013/14
Cabinet Date: 10 February 2010
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.