Resolved

Resolved – (1) That the contents of the joint report on the Swindon Capita Partnership, and the successes since the last Cabinet update in September 2008, be noted in particular: § That Swindon Direct has achieved accreditation from The Customer Contact Association, an independent industry standards body, in 2009 and 2010 for the Customer Contact Centre and One Stop Shop and has achieved a 97% Customer satisfaction rating; § The significant improvements in the performance of the Housing Benefits Service, acknowledged by the Department of Work and Pensions, since the Audit Commission Report in April 2009, as set out in paragraphs 2.15 to 2.20 of the joint report; § The programme of ICT infrastructure replacement as referred to in paragraphs 2.9, 2.10 and 2.11 of the joint report; § Savings of £1.2m already delivered through a lower service charge during the first 3 years of the partnership and additional savings identified and enabled to date of £6.4m, as set out in paragraph 2.21 of the joint report; § The introduction of an Partnership Scorecard based on industry best practise to measure the ‘health’ of the partnership, that has allowed the partnership to take targeted action towards improvement; and § The 97.1% success rate against the 92 Key Performance Indicators that are used as performance measures for the eleven services currently delivered by the Partnership. (2) That it be noted that the Swindon Capita Partnership is seeking significant improvements and efficiencies in the delivery of relevant building schemes in the Capital Programme 2010 / 2011 by working with the Project Management Office to address the project lifecycle, demand, commissioning, build and handover, as ... view the full minutes text for item 129. (CM: GP)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet

Swindon Capita Partnership; Progress, Achievements and Challenges CABINET Date: 14 April 2010

Author: Cabinet Member for Leisure and Corporate Services and the Group Director, Business Transformation

Parish / Wards Affected: All

Purpose • To inform Cabinet on progress made since September 2008 by the Swindon Capita partnership including; key achievements, service improvements, contribution to the Council’s transformation programme as well as its medium term financial plan and future challenges.

Recommendation Cabinet is requested to: • Note the report and the successes since the last Cabinet update in September 2008, in particular:  That Swindon Direct has achieved accreditation from The Customer Contact Association (CCA) an independent industry standards body in 2009 and 2010 for the Customer Contact Centre and One Stop Shop and a 97% Customer satisfaction rating.  The significant improvements in the performance of the Housing Benefits Service, acknowledged by the Department of Work and Pensions since the Audit Commission Report in April 2009 as set out in paragraphs 2.15 to 2.20  The programme of ICT infrastructure replacement as set out in paragraphs 2.9, 2.10 and 2.11.  Savings of £1.2m already delivered through a lower service charge during the first 3 years of the partnership and additional savings identified and enabled to date of £6.4m as set out in paragraph 2.21.  The introduction of an Partnership Scorecard based on industry best practise to measure the ‘health’ of the partnership, that has allowed the partnership to take targeted action towards improvement.  The 97.1% success rate against the 92 Key Performance Indicators that are used as performance measures for the 11 services currently delivered by the Partnership.

• Note that the Partnership is seeking significant improvements and efficiencies in the delivery of relevant building schemes in the Capital Programme 2010 / 2011 by working with the Project Management Office (PMO) to address the project lifecycle; demand, commissioning , build and handover as set out in paragraph 2.14.

Further information on the subject of this report can be obtained from Sue Mendham on 01793 464932 or Email [email protected]. Swindon Capita Partnership; Progress, Achievements and Challenges CABINET Date: 14 April 2010

• Approve the focus and note the challenges for the year 2010/11: service improvement, reduced cost and partnership growth as set out in paragraph 2.34.

• Note the Annual Report for the Swindon Capita Partnership as outlined in Appendix 1.

1. Reasons 1.1 The Council entered into a 15-year strategic partnership on 1 February 2007 and the aim of this report is to inform Members on the performance of the partnership since the last report to Cabinet in September 2008.

2. Detail

2.1In the last report to Cabinet, Members were updated on the first 18 months of the Swindon Capita partnership, setting out the significant achievements and the key challenges that had been faced by the parties. This report further updates Members on progress since autumn 2008.

2.2Over the last 18 months key achievements include:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Swindon Capita Partnership Annual ReportAppendix 1 1.1 MB Download
PDF
Swindon Capita Partnership: Progress, Achievements and ChallengesReport 88 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. Swindon Capita Partnership: Progress, Achievements and ChallengesThis decision
  2. Capital Funding Request - Swindon Housing CompanyAgreed
  3. Future Direction of Swindon Capita Partnership.Noted
  4. Swindon Capita Partnership: Progress, Achievements, Challenges 2011 - 2013Noted
  5. Swindon Capita Partnership - Progress, Achievements, Challenges 2010 - 2012Approved
  6. Update on Swindon Capita PartnershipNoted

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies