Resolved
Resolved – (1) That the progress made by AWP against the targets set and the actions identified be noted. (2) That AWP look at presenting the data in a better format, with the inclusion of a narrative.
Joint Commissioning Board (Adult Services) noted this item on Tuesday 16 November 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – (1) That the progress made by AWP against the targets set and the actions identified be noted. (2) That AWP look at presenting the data in a better format, with the inclusion of a narrative.
2.1The JCB is asked to note the progress made by AWP against the targets set and the actions identified
3.1The balance scorecard targets are agreed within the block contract therefore there are no financial implications
4 Social, Environmental, Staffing and Legal/Human Rights Implications
4.1None
5 Detail
5.1Swindon AWP Balanced scorecard reported 19 indicators within the red category at the end of June 2010, Quarter 1. Of these 14 were new indicators agreed as part of the 2010/11 contract.
5.2Each of the 19 indicators had a delivery plan in place to ensure progress towards the target was achieved during Quarter 2.
It is to be noted that due to the first stage of RiO implementation, with the Older Peoples SBU (OP), the scorecard data presented does include data for OP SBU however it is frozen at the last known position as reported for Quarter 1. There are now seven more indicators included in the Quarter 2 scorecard that contain up to date OP services data sourced from RiO via the data warehouse. By Month 7 it is expected that all CQUIN and Penalty indicators will be reported on from the data warehouse. Not for Publication
During Quarter 2 there was a more rigorous process of performance monitoring implemented at Adults SBU Operational Level. This process included weekly reporting against each of the red indicators in order to ensure improvements in performance. This has resulted in significant improvements against some of the indicators as detailed below.
5.3Improvements in performance of particular note are:
5.3.1 Discharge letter within 48 hrs of discharge - 2.2.13
This new indicator measures compliance with AWP’s Discharge protocols, which ensures that the GP and patient receive a letter within 48 hours of discharge. This applies to in-patient and community services for all referrals and cases returned to GP. The target for this is 98% and at the end of Quarter 1 performance was at 23.3%. Although reporting against this indicator is a new requirement within the balanced scorecard this practice has been in place for some time. However, there had not been the necessity to collect performance electronically until this year. There has been significant work undertaken by the Adults and the OP SBUs to ensure that this is now in place and the position at the end of Month 5 is reported to have improved to 76%. It is expected that the actual position is better than that reported, as letters will have been sent as required but not inputted onto the electronic system. Although, still below the target there has been a significant improvement.
5.3.2 % service users on CPA - 2.2.15
The current performance against this indicator remains lower than the target of 80% which illustrates the caseload profile of the Adult CMHT. This includes a significantly large number of patients on Non CPA who are open to Consultant Psychiatrists. The performance of 49% at the end of Quarter 1 has improved to 66% at the end of September following the intense weekly monitoring process within the Adult SBU.
5.3.3 % service users with a care plan - 2.2.03 This indicator has being monitored weekly as part of the Adult SBU week on week performance review and performance has improved with the SBU to 89% in October moving towards the target of 98%.
5.3.4 % service users receiving a review - 2.2.10
Performance against this indicator is also impacted by the number of Non CPA service users on the Consultants caseload and at Quarter 2 Not for Publication
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AWP Balance ScorecardReport | 5 pages | DownloadRead as text |
PDF |
scorecard Sept 10 v2 MH budgetAppendix 1balance | 1 pages | Download |
Follow Joint Commissioning Board (Adult Services) at Swindon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Mar 2012 | Financial Position as at 31st January 2012 - Mental Health Aligned Budget for 2011/12Resolved – That the financial position as at January 2012 for the aligned budget be noted, together with any recommen... | Noted | Open |
| 27 Mar 2012 | Avon and Wiltshire NHS Partnership Trust Balanced Scorecard ReportResolved – That the Board notes the performance to date, together with the areas of improvement and the actions requi... | Decided | Open |
| 27 Mar 2012 | Financial Position as at 31st January 2012 - Adult s75 Commissioning - Adult Community Services 2011/12Resolved – That the financial position as at 31st January 2012 of the Adult Community aligned budget 2011/12 be noted. | Noted | Open |
| 27 Mar 2012 | Financial Position to 31st January 2012 - Adult s75 Commissioning - Learning Disability Services 2011/12Resolved – That the financial position as at 31st January 2012 for the Learning Disability aligned budget 2011/12 be ... | Noted | Open |
| 27 Mar 2012 | Joint Commissioning Boards arrangements across Children and Adult ServicesResolved – (1) That Council and the NHS Swindon and Gloucestershire Cluster Board be recommended to approve that: (a)... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.