Resolved – (1) That the current projected Revenue Budget Outturn, as set out in Table 1 of the joint report, be noted. (2) That the Revenue Budget virements, as set out in Appendix 2 to the joint report, be approved. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: DR / ME)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member for Finance and Director of Finance
Purpose This report presents the 2010/11 Revenue forecast out-turn at the end of January 2011.
Recommendation That Cabinet; o Notes the current projected outturn set out in Table 1; o Approves the virements in Appendix 2. 1 Reasons General Fund Revenue Account 1.1 The report updates Cabinet on the current forecast position of the Council’s Revenue Budgets. The forecasts are based on data as at the end of January 2011. 2 Detail 2.1 The report presents the General Fund Revenue forecast outturn for 2010/11 based on the January 2011 monitoring data. 2.2 As reported to Cabinet in December 2010, Groups had allowed at that stage for the impact of known risks within their year-end positions whilst still working on plans to mitigate the impact of these risks. This has led to overall improvements in the reported position for all Groups except for Adult Social Care. General Fund Revenue Forecast Outturn for 2010/11 2.3 The General Fund Revenue forecast outturn for 2010/11 based on the January 2011 monitoring data is shown in Table 1 below with a more detailed analysis shown at Appendix 1. The main changes are an increased overspend on Adult Social Care, mitigated by increased projected underspends on Business Transformation and Children’s Services. In overall terms, there is a net improvement of £0.2m with a Council-wide projected underspend of £1.2m, subject to Cabinet’s decision relating to Highworth Recreation Centre elsewhere on this agenda..
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Revenue Budget Management 2010/11
Cabinet Date: 9th March 2011
Table 1: General Fund Forecast Budget Forecast Forecast Movement 2010/11 Outturn Variance since last report £’000 £’000 £’000 £’000 Children Services 28,189 27,736 (453) (152) Housing, Leisure, Libraries and Culture 13,352 13,929 577 (60) Adult Social Care 40,358 42,558 2,200 200 Environment, Regeneration & Communities 29,845 29,347 (498) (28) Business Transformation 16,849 16,705 (144) (165) Sub Total of Groups 128,593 130,275 1,682 (205) Chief Executive & Corporate (275) (213) 62 (2) Sub Total 128,318 130,414 2,096 145 Contingency Fund/Severance 2,908 0 (2,908) 0
Total 131,226 130,062 (1,164) (207)
3 Group Directorate Summaries 3.1 Explanations of the key issues reflected in the different service areas are provided below. Children Services 3.2 The January forecast shows an under spend of £453k which is an improvement of £152k since the last report. 3.3 The main reasons for this improvement are:- • Savings identified in relation to Special Educational Needs (SEN) transport costs. This has been achieved as a result of a reduction in costs following the review the transport routes coupled with a reduction in the numbers of children in out of Borough care in receipt of transport. • Savings in relation to Youth Opportunities Funding as a result of demand for project funding being lower that previously anticipated. Housing, Leisure, Libraries & Culture 3.4 The January forecast shows a projected overspend of £577k, which is an improvement of £60k since the last report. 3.5 This improvement consists of a number of minor variances across the Group as a result of continued managements actions to identify savings. 3.6 The figures shown do not include any allowance for writing off the debt for Highworth Recreation Centre. Should Cabinet approve the proposal elsewhere on the agenda, this would result in an additional adverse variance of £460k.
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Revenue Budget Management 2010/11
Cabinet Date: 9th March 2011
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.