Resolved – (1) That the Capital Out-turn position for the 2010/11 Financial Year and the Capital Programme for 2011/12, be noted. (2) That the Treasury Management performance for the 2010/11 Financial Year and the Prudential Indicators be noted. (3) That the Council retains possession of the Mechanics Institute in order to enforce the Council’s charge over that property to recover the costs and expenses incurred by the Council, referred to in paragraph 2.4 of the joint report, in carrying out works to remove the danger resulting from its dangerous ... view the full minutes text for item 6. (CM: PG / NM)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Capital Programme 10/11 Outturn and 11/12 Programme - Treasury Management Performance 2010/11
Cabinet Date: 8th June 2011
Author: Cabinet Member for Finance and Director of Finance
Purpose This report presents the 2010/11 Capital Out-turn position, the Capital Programme for 2011/12 and the Treasury Management performance for 2010/11.
Recommendation That Cabinet: 1.Notes the 2010/11 Capital Out-turn position and Capital Programme for 2011/12; 2.Notes the 2010/11 Treasury Management performance and Prudential Indicators; 3.Agrees that the Council retains possession of the Mechanics Institute in order to enforce the Council’s charge over that property to recover the costs and expenses incurred by the Council referred to in paragraph 2.4 of this Report in carrying out works to remove the danger resulting from its dangerous condition; 4.Approves the changes to the Capital programme detailed at paragraphs 2.8 to 2.12; 5.Delegates authority to the Group Director Business Transformation, in consultation with the Director of Finance, the Cabinet Member for Finance and the Cabinet member for Sustainability, Strategic Planning, Property and Transport to agree settlement for Wichelstowe Contract 4 in line with the approach detailed at paragraphs 2.17 to 2.20; and 6.Approves the approach to Wichelstowe S106 contributions detailed at paragraphs 2.21 to 2.23.
1 Reasons 1.1 To update the Cabinet on the Capital Out-turn position for 2010/11, the Capital Programme for 2011/12 and Treasury Management performance for 2010/11. 2 Detail Capital Programme 2.1 In 2010/11, capital expenditure amounted to £84.2 million against a budget of £117.6 million. This is a similar level of expenditure to the previous financial year when £84.6million of capital expenditure was incurred. Tables 1 & 2 below give a breakdown of the 10/11 spend and variances, by Group Directorate, together with an indication of the previous reported forecast position. Table 3 shows details of how the
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No. 463976 or Email [email protected] Capital Programme 10/11 Outturn and 11/12 Programme - Treasury Management Performance 2010/11
Cabinet Date: 8th June 2011
programme was funded. Appendix 1 gives detailed outturn on a scheme-by-scheme basis and appendix 2 shows the detailed Capital Programme for 2011/12. The current Capital Programme position will in future be detailed and updated regularly through the PMO area of the Council’s intranet site, under the heading “Finance Capital Monitoring”. Table 1 - Capital Programme Out-turn 2010/11 Net Re- Total Savings Overspends Phasing variance Group £'000 £'000 £'000 £'000 Children's Services (1,254) 1,605 (13,218) (12,867) Environment & Regen. (764) 1,016 (13,797) (13,545) Housing & Leisure (21) 29 646 654 Adult Social Care (1) 0 (3,530) (3,531) Business Transformation (756) 3,575 (7,120) (4,301) Totals (2,796) 6,225 (37,019) (33,589)
2.2Table 2 – Analysis of Capital Programme Variance 2010/11 Forecast 2010/11 Actual @ Feb % Actual/ Budget to Date Variance 2011 Forecast Group £'000 £'000 £'000 £'000 £'000 Children's Services 33,762 20,895 (12,867) 21,799 96% Environment & Regen. 34,397 20,852 (13,545) 23,944 87% Housing & Leisure 9,191 9,845 654 8,924 110% Adult Social Care 6,183 2,652 (3,531) 4,477 59% Business Transformation 34,262 29,961 (4,301) 32,861 91% Service Totals 117,795 84,206 (33,589) 92,005 92%
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.