Resolved – (1) That the current projected Revenue Budget Out-turn, as set out in Table 1 of the joint report, be noted. (2) That the allocation of £25,000 to fund an Independent Reviewing Manager post from the specific contingency created for Children’s Services to provide for risks against White Paper and other impending future legislative changes and demand volatility, be noted. (3) That the transfer of the specific contingency fund for Adult Services, as set out in paragraph 3.12 of the joint report, into the main operational budget for Adult Social Care, be noted. (4) That a capital budget of £300,000 to deliver a community centre at East Wichel, to be funded from Corporate Capital Resources, as referred to in paragraph 3.14 of the joint report, be approved. (5) That the Revenue Budget virements, as set out in Appendix 2 to the joint report, be approved. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: BM)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member for Finance and Director of Finance
Parish / Wards Affected: All
Purpose • This report presents the 2011/12 Revenue forecast out-turn at the end of May 2011.
Recommendation That Cabinet; • Notes the current projected out-turn set out in Table 1;
• Notes the allocation of £25k to fund an Independent Reviewing Manager post from the specific contingency created for Children’s Services to provide for risks against White Paper changes and demand volatility;
• Notes the transfer of the specific contingency fund for Adult Services as set out in paragraph 3.12 into the main operational budget for Adult Social Care;
• Approves a capital budget of £300k to deliver a community centre at East Wichel, to be funded from Corporate Capital Resources.
• Approves the virements set out in Appendix 2.
1 Reasons 1.1 To update Cabinet on the current forecast position of the Council’s Revenue Budgets based on data as at the end of May 2011. 2 Detail 2.1 The General Fund Revenue forecast out-turn for 2011/12 based on the May 2011 monitoring data is shown in Table 1 below with a more detailed analysis shown at Appendix 1. The budget figures reflect the budget changes approved by Cabinet on 8th June 2011. 2.2 The current forecast is an overspend of £143k. The key variances within this figure is a shortfall in income from Residents car parking permits, Recreation and Lydiard Country Park and a lower than forecast level of savings from Waste to Energy which are partly offset by targeted savings on contracts.
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Revenue Budget Management 2011/12
Cabinet Date: 13th July 2011
Table 1: General Fund Forecast
Budget Forecast Forecast Over/ 2011/12 Out-turn (Under) spend £’000 £’000 £’000 Children Services 31,445 31,445 0 Housing, Leisure, Libraries and 12,985 13,128 143 Culture Adult Social Care 42,107 42,107 0 Environment, Regeneration and 29,480 29,480 0 Communities Business Transformation 18,648 18,648 0 Sub Total of Groups Position 134,665 134,808 143 Chief Executive & Corporate 429 429 0 Sub Total 135,094 135,237 143 General Contingency Fund 2,328 2,328 0 Total 137,422 137,565 143
3 Group Directorate Summaries 3.1 Explanations of the key issues reflected in the different service areas are provided below. Children Services 3.2 The Group is currently forecasting a balanced budget. However there are two key areas that are under review:- o Social Care / Adoption Placements – the 2011/12 placement budgets were set to meet demand as at December 2010 and, unless there is a significant increase in demand it should be possible to contain any in year pressures. However if demand for the service increases, it may be necessary to seek Member approval to make an allocation from the £250k White Paper contingency and demand volatility budget. o Home to School Transport – further work is required to refine these projections which will be affected by September pupil changes but a year- end underspend is highly probable. Adult Social Care 3.3 Following the approval of additional budget by Cabinet on 8th June 2011, Adult Social Care is reporting a balanced position. The key area of risk within the service is on the cost of care packages and a number of key changes have been made to the way in which new care is agreed within the service. A clear commissioner / provider split of the service now positions the commissioners with the final sign off of all care packages. This new processes is expected to help the Council manage the rising costs of care packages and this is an area that will be kept under review in the coming months.
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Revenue Budget Management 2011/12
Cabinet Date: 13th July 2011
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.