Resolved – (1) That the position of the Council’s 2011/12 Capital Programme and in particular the variances detailed at paragraphs 2.5 to 2.9 of the joint report, be noted. (2) That the proposed changes to the Capital Programme, as detailed in paragraphs 2.14 to 2.16 of the joint report, plus the reduction in the budget for the two-form of entry primary school on the Croft Site to £5m, as shown in Appendix 1 to reflect the latest cost estimate, be approved. (3) That the Group Director, Children, in consultation with the Director of Finance and the Cabinet Member for Children’s Services, be authorised to submit a bid to the Department for Education for capital funding for the relocating and rebuilding Crowdy’s Hill School, as detailed at paragraphs 2.17 to 2.21 of the joint report. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: DR)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member for Finance and Director of Finance
Parish / Wards Affected: All
Purpose • To present the latest position on delivery and funding of the Council’s current approved Capital Programme.
Recommendation That Cabinet: 1. Notes the position of the 2011/12 Capital Programme, and in particular the variances detailed at paragraphs 2.5 to 2.9;
2. Approves the proposed changes to the Capital Programme detailed at paragraphs 2.14 to 2.16;
3. Authorises the Group Director, Children in consultation with the Director of Finance and the Cabinet Member for Children’s Services, to submit a bid to the Department for Education for capital funding for relocating and rebuilding Crowdy’s Hill School, as detailed at paragraphs 2.17 to 2.21.
1 Reasons 1.1 To update the Cabinet on the current Capital Programme position and the projected 2011/12 Capital Programme out-turn position. The forecasts are based on data as at the end of June 2011. 1.2 To update the Cabinet on changes made to the Capital Programme since it was last brought to Cabinet in June 2011.
2 Detail 2.1 The Capital Programme for 2011/12 is summarised in Table 1 below.
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No. 463976 or Email [email protected] Capital Programme Monitoring
Cabinet Date: 7th September 2011
Table 1: Capital Expenditure and Forecasts 2011/12
2011/12 Current Projected Actual % Actual / Budget Forecast Variance to Date Forecast Group £'000 £'000 £'000 £'000 £'000 Children's Services 19,198 17,841 (1,357) 2,689 15% Environment, Regeneration and Community 35,490 24,453 (11,037) 841 3% Housing, Leisure, Libraries and Culture 11,108 11,123 15 (1,312) - Adult Social Care 2,246 2,237 (9) 557 25% Business Transformation 16,650 16,077 (573) 2,570 16% Service Totals 84,692 71,731 (12,961) 5,345 7%
2.2The actual spend to date figure of £5.345m in Table 1 is reduced by a significant amount of outstanding creditor provisions, estimated at £3m, from the previous financial year. The total creditor provision at the end of March 2011 was £6.96m. 2.3 Significant work has been carried out by finance staff and project managers to ensure that in-year forecasts are realistic. This is reflected in the significant variation shown in the table above between the current forecast of £71.7m and the 2011/12 original budget of £84.7m. 2.4 An analysis of the annual out-turn figures compared to forecasts at various points in the year over the last two years, shows that the out- turn is generally around 80% of the in-year forecast. If this trend continues, an out-turn figure of around £57m is likely for 2011/12, ignoring the impact of any further budget approvals. Table 2 – Analysis of Capital Programme Variance 2011/12 Forecast Potential Potential Net Re- Total Savings Overspends Phasing variance Group £'000 £'000 £'000 £'000 Children's Services (60) 897 (2,194) (1,357) Environment, Regeneration and Community (7,463) 1,016 (4,589) (11,037) Housing, Leisure, Libraries and Culture - 15 - 15 Adult Social Care (10) - - (9) Business Transformation - - (573) (573) Totals (7,533) 1,928 (7,356) (12,961)
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No. 463976 or Email [email protected] Capital Programme Monitoring
Cabinet Date: 7th September 2011
Details of Projected Variances 2.5 The forecast 2011/12 underspend against budget of (£1.357m) for Children’s Services is made up of: • (£60k) of potential savings - several minor savings on capital schemes
• £897k of potential overspends including: o £411k Swindon Academy (actual overspend of £750k on 0-4 & 4-11 mitigated by other academy related savings of £339k) o £319k of overspends on projects completed in previous years. o £154k relating to further expenditure on 2 schemes previously reported as complete, £53k Millbrook School & £99k Oakhurst School
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.