Resolved (1) That, based on information available at the end of August, the in year projected overspend of £198,000 on the retained DSG budget, be noted (2) That an Early Years Sub-Group be appointed comprising of representatives from primary schools and the private, voluntary and independent sector to discuss the Early Years Funding Formula. (3) That the Forum agrees the allocation of the 2010/11 retained budget underspend of £49,492 to ameliorate the projected 2011/12 overspend. (4) That the Forum agrees to provisionally allocate the unspent Standards fund balance of £234,944 to further alleviate the projected 2011/12 overspend . (5) That the Forum agrees to the Local Authority developing proposals for the reduction of centrally retained spending on schools in challenging circumstances and redundancies/early retirements. (6) That the Forum agrees that any funding released from the retained budget in 2012/13 is applied an inflationary uplift across all 2012/13 funding factors other than those areas where specific funds are delegated to named schools.
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Retained Dedicated Schools Grant (DSG) Budget Position 2011-12 and 2012-13 Proposals Schools Forum 11 October 2011 Author: Group Finance Manager – Children Services Parish / Wards Affected: All
Purpose • To advise Schools Forum members of the latest position on the 2011/12 retained Dedicated Schools Grant (DSG) budget and to outline proposals for reducing retained spending in 2012/13.
Recommendations The Schools Forum is requested to: • Note that, based on information available at the end of August, an in year overspend of £198,000 is projected against the retained DSG budget • Agree to the establishment of an Early Years Sub Group to identify options to reduce pressure on the Early Years Single Funding Formula • Agree to earmark funding carried forward from an underspend on the 2010/11 retained budget totalling £49,492 against the projected overspend • Agree to provisionally earmark unspent Standards fund grants of up to £234,944 against the projected overspend • Agree in principle to support the areas proposed by the Local Authority (LA) to reduce retained spending next year • Agree that any funding released from the retained budget is applied as an inflationary uplift across all 2012/13 funding factors, other than where specific funds are delegated to named schools.
1. Reasons 1.1 At the March 2011 Schools Forum meeting the retained DSG budget for 2011/12 was agreed at £19.007m and this report provides Forum members with the latest information on spending against this budget. Due to pressures in some areas an in year overspend is projected and mitigating actions are explained in this report which include the allocation of funds carried forward from 2010/11. The LA will continue to take action wherever possible to minimise spending against the retained budget in order to avoid carrying forward an overspend to 2012/13.
1.2The LA made a commitment last year to minimise the value of the retained DSG budget and agreed a series of increased delegations to schools which were reflected in the 2011/12 budget. Although there is demand led pressure in some areas of the retained budget there are other areas where the LA feels that reduced central spending is possible as summarised in this report.
Further information on the subject of this report can be obtained from Steve Haley on 01793 465794 or Email [email protected]. Retained Dedicated Schools Grant (DSG) Budget Position 2011-12 and 2012-13 Proposals Schools Forum 11 October 2011 2. Detail
Current Year Budget Position
2.1The retained DSG budget is monitored in accordance with standard Swindon Borough Council (SBC) budgetary control procedures and a report containing revised projections for every service area is submitted to the Children Services Leadership Team (CSLT) each month. Updates are also provided to Corporate Board, Cabinet and the Children and Young Peoples Overview and Scrutiny Committee.
2.2Attached at Annex A is a copy of the report submitted to CSLT on 24th August which highlighted key areas of concern on the retained DSG budget and concluded that an in year overspend of £198,000 was projected at that time. Although a number of forecasts have subsequently been refined the overall position is unchanged and a commentary on the key pressure areas is provided below;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.