Swindon Borough Council
Cabinet, Wednesday 19 October 2011

Swindon Sustainable Energy Delivery Plan

Noted Executive 2 papers

Cabinet noted this item on Wednesday 19 October 2011. Below is the council's own wording, with the papers it was decided on.

Item49

Resolved

Resolved – (1) That the Sustainable Energy Delivery Plan, attached as Appendix 1 to the joint report, and the activities and timescales set out at Annex A to that Delivery Plan, be noted and approved. (2) That the Deputy Chief Executive and Group Director, Environment, Regeneration and Communities be authorised to – o Undertake further District Energy feasibility work at a cost of no more than £15,000, and subsequent “soft market testing”, with a view to preparing District Energy business model options for Swindon, and o Submit a further report to the Cabinet setting out business model options for progressing a District Energy Network in Swindon. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: GP)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet, 5 pages

Swindon Sustainable Energy Delivery Plan CABINET Date: 19th October 2011

Author: Cabinet Member for Council Transformation, Sustainability, Transport and Strategic Planning and Deputy Chief Executive and Group Director, Environment, Regeneration and Communities.

Parish / Wards Affected: All

Purpose • To seek Cabinet approval for the Swindon Sustainable Energy Framework Delivery Plan.

Recommendation • To approve the Sustainable Energy Delivery Plan (Appendix 1) with particular reference to the activities and timescales set out at Annex A of the Delivery Plan.

• To authorise the Deputy Chief Executive and Group Director, Environment, Regeneration and Communities to o undertake further district energy feasibility work at a cost of no more than £15k, and subsequent soft market testing, with a view to preparing district energy business model options for Swindon; and o bring back a report to the Cabinet setting out business model options for progressing a district energy network in Swindon.

1. Reasons

1.1On 8th June 2011, Cabinet Members approved the Swindon Sustainable Energy Framework as a local response to the priority issues of energy cost, energy security and CO2 reduction. The Framework sets out key principles around how energy projects should be co-ordinated and shaped to maximise local community and business benefit.

1.2The same Cabinet meeting authorised the production of a delivery plan, the subject of this report, which provides practical detail on how the energy related activities across Swindon can move forward in a co-ordinated way.

2. Detail

2.1The Swindon Sustainable Energy Framework was adopted by the Cabinet on the 8th June 2011 as a local response to the three key energy issues of rising costs, the need for secure energy supplies and the requirement to reduce CO2 emissions.

Further information on the subject of this report can be obtained from Stephen Cains on 01793 466405 or Email [email protected]. Swindon Sustainable Energy Delivery Plan CABINET Date: 19th October 2011

2.2The Cabinet report of the 8th June 2011 sets the rationale behind the local approach to energy issues but, in summary, the focus of the Framework is on a more co-ordinated approach to renewable energy infrastructure and securing the economic benefits around jobs and skills of a move to more sustainable energy supplies.

Swindon Sustainable Energy Framework: Delivery Plan

2.3Whilst the Sustainable Energy Framework sets down the principles, the Delivery Plan at Appendix 1 sets out the practical activities to bring forward renewable energy infrastructure and to maximise related skills and jobs in Swindon. Some projects are already underway and the progress is reflected in the table at Annex A of the Delivery Plan.

2.4The Delivery Plan at Appendix 1 has been prepared in close co-operation with key businesses and stakeholders in Swindon including Forward Swindon, BMW Group, Honda UK, Honda Trading, Kilbride, Network Rail the Great Western Hospital. The success of the plan will depend on ongoing cooperation with these, and other stakeholders as the project progresses.

2.5It is important to note that the Delivery Plan represents one step toward securing a more sustainable energy future in Swindon. Success will be dependent on the commitment of the Council and its partners and how projects are co-ordinated and shaped. Therefore, alongside activities identified in the Delivery Plan, a set of principles has been developed to guide and challenge project activities. The principles draw on the One Swindon priorities and are as follows:

• Local control – local benefits • Collaboration • Effective resource use • A long term perspective • Managed risk • Flexibility • Learning together

Delivering Energy Infrastructure

2.6The benefits of a move to more sustainable forms of energy are clear. However, delivering new renewable energy infrastructure will be a major challenge. The Council has a key facilitation role to play here and the Delivery Plan focuses on the following areas of activity:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Swindon Sustainable Energy Framework Delivery Plan 2011Appendix 1 10 pages Download
PDF
Swindon Sustainable Energy Delivery PlanReport 5 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 13 attended
RB
Councillor Roderick BluhChair, present
GP
Councillor Garry PerkinsVice-Chair, present
ME
Councillor Mark EdwardsMember, present
PG
Councillor Peter GreenhalghMember, apologies
RH
Councillor Russell HollandMember, present
CL
Councillor Colin LovellMember, apologies
BM
Councillor Brian MattockMember, apologies
NM
Councillor Nick MartinMember, present
DR
Councillor David RenardMember, apologies
KW
Councillor Keith WilliamsMember, present
KP
Councillor Kevin ParryCabinet Member attendee, in attendance
BW
Councillor Bob WrightCabinet Member attendee, in attendance

All 13 on the meeting page

On this subject at Swindon

Search all
  1. Swindon Sustainable Energy Delivery PlanThis decision
  2. Securing a sustainable future for Swindon's Library ServicesNoted
  3. Securing a sustainable future for Swindon's Library ServicesNoted
  4. Swindon Sustainable Energy Framework and Photovoltaic Installation OpportunityApproved
  5. Swindon Sustainable Design and Construction Supplementary Planning Document (SPD)Noted
  6. Swindon Sustainable Design and Construction Supplementary Planning Document (SPD) (revised draft)Decided

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies