Resolved – (1) That the current projected Revenue Budget Outturn, as set out in Table 1 of the joint report, be noted. (2) That a 12 month extension of the Youth Offending Early Intervention Team be agreed to be funded by carrying forward £110,000 from the current Financial Year’s underspend in Children Services. (3) That the Revenue Budget virements , as set out in Appendix 2 to the joint report, be approved. (4) That the Council funds the preparation and filing of the Digital City UK Ltd.’s accounts, as detailed in paragraph 4.1 of the joint report . (5) That, s ubject to the Council’s final out-turn position permitting, Swindon Commercial Services Ltd. (SCS) retain a further £300,000 of profit generated in order to improve its balance sheet position and hence secure further external contracts. (6) That the Director of Planning and Transport be authorised to take the necessary actions to end as quickly as possible the trial switching off of some street lights during non-peak times, in line with the proposal contained within the 2012/13 Budget proposal at Item 9 on this agenda. (Councillor Garry Perkins, Deputy Leader of the Council and Cabinet Member for Regeneration and Culture, made a personal declaration of interest in respect of the above item, as he was a Council appointed Non-Executive Director on the Board of Swindon Commercial Services (SCS) Ltd.) The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: ME)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member for Finance and Director of Finance
Parish / Wards Affected: All
Purpose • This report presents the 2011/12 Revenue forecast out-turn at the end of December 2011.
Recommendation That Cabinet: • Notes the current projected out-turn set out in Table 1; • Agrees to fund a 12 month extension of the Youth Offending Early Intervention Team by carrying forward £110k from the current year’s underspend in Children Services; • Approves the virements set out in Appendix 2; • Agrees that the Council funds the preparation and filing of the Digital City UK accounts, as detailed in paragraph 4.1; and • Subject to the final out-turn position permitting, agrees that Swindon Commercial Services Ltd. should retain a further £300k of profit generated in order to improve its balance sheet position and hence secure further external contracts. 1 Reasons 1.1 To update Cabinet on the current forecast position of the Council’s Revenue Budgets based on data as at the end of December 2011. 2 Detail
2.1The General Fund Revenue forecast out-turn for 2011/12 based on the December 2011 monitoring data is shown in Table 1 below with a more detailed analysis shown at Appendix 1. 2.2 The Council is currently reporting an underspend of £1,491k, an improvement of £991k since the last report. In the context of the Council’s challenging medium- term financial position, budget managers have been extremely prudent in entering into new financial commitments in the current year. This, together with early delivery of the efficiency measures contained within the 2012/13 budget, enabled by the accelerated timetable for the budget proposals, and more stringent financial controls has resulted in early confirmation of an improved year end forecast position. The specific factors contributing to this improvement are explained in section 3 of this report.
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Revenue Budget Management 2011/12
Cabinet Date: 15th February 2012
Table 1: General Fund Forecast Budget Forecast Forecast Movement 2011/12 Out-turn Over/ (Under) since last spend report £’000 £’000 £’000 £’000 Children Services 31,484 29,838 (1,646) (291) Housing, Leisure, Libraries and Culture 13,338 13,443 105 (168) Adult Social Care 43,598 43,598 0 0 Environment, Regeneration and 29,567 29,267 (300) (200) Communities Business Transformation 18,285 17,348 (937) (632) Sub Total of Groups Position 136,272 133,494 (2,778) (1,291) Chief Executive & Corporate (143) (156) (13) 300 Sub Total 136,129 133,338 (2,791) (991) General Contingency Fund 1,293 2,593 1300 0 Total 137,422 135,931 (1,491) (991)
3 Group Directorate Summaries 3.1 Explanations of the key issues reflected in the different service areas are provided below. Children Services 3.2 The Group is currently projecting an underspend of £1,646k, an improvement of £291k since the last report. 3.3 Within this projection cost pressures have arisen relating to the on-going support for asylum seeking children and funding for Youth Offending Early Intervention Team mitigated by: • Additional income from traded services; • Further savings arising from early years budgets largely relating to a reduction in funding required for Penhill and Pinehurst Sure Start Centre and further reductions in sustainability, inclusion and workforce development budgets; • Further savings arising on mainstream transport as a result of lower take- up than anticipated; • Cross group vacancy savings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.