Resolved – (1) That the Director for Planning and Transport be authorised to award individual schemes to Swindon Commercial Services Ltd., as set out in the programmes in Appendices A, B and C to the report and that the Council’s Contract Standing orders be waived accordingly. (2) That it be noted that contracts subject to OJEU can only be dealt with in this way whilst Swindon Commercial Services is ‘ Teckal ’ compliant. (Councillor Garry Perkins, Deputy Leader of the Council and Cabinet Member for Regeneration and Culture, made a personal declaration of interest in respect of the above item as he was a Council appointed Non-Executive Director on the Board of Swindon Commercial Services (SCS) Ltd.) The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: RB)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Award of Highways, Transport and Landscape Schemes to Swindon Commercial Services Limited. CABINET Date: 21st March 2012
Author: Cabinet Member for Council Transformation, Sustainability, Strategic Planning and Transport and Director of Planning and Transport
Parish / Wards Affected: All
Purpose • To seek authority to award works for highways, transport and landscape projects to Swindon Commercial Services Ltd (SCS) for the 2012/13 programme of works.
Recommendation Cabinet is requested to • Authorise the Director for Planning and Transport to award individual schemes to Swindon Commercial Services Ltd as set out in the programmes in Appendices A B and C to the report and that Contract Standing orders be waived accordingly, and • Note that contracts subject to OJEU can only be dealt with in this way whilst SCS is ‘Teckal’ compliant.
1. Reasons 1.1 To ensure transparency of decision making and the best value delivery of works awarded to Swindon Commercial Services Ltd (SCS).
2. Detail 2.1 In February 2011 the Cabinet approved the Capital Programme for 2011/12 – 2013/14. The Capital Programme included a range of highway and transport schemes that have in recent years been delivered through a combination of competitive tender or awarded to Swindon Commercial Services Ltd. (SCS) without tendering. A breakdown of the capital spend identifying the anticipated value of work recommended to be awarded directly to SCS in 2012/13 is included in Appendix A, together with a number of schemes funded from revenue.
2.2Similarly to the highway and transport schemes outlined above, SCS have in recent years been awarded programmes of landscape works without tendering. Appendix B contains a programme of Section 106 funded landscape works recommended to be awarded to SCS in 2112/13, including 2 schemes given capital approval in February 2012.
Further information on the subject of this report can be obtained from Tim Price on 01793 466254 or Email [email protected]. Award of Highways, Transport and Landscape Schemes to Swindon Commercial Services Limited. CABINET Date: 21st March 2012
2.3Local Transport Plan (LTP) integrated schemes will be selected from a pool of schemes included in the proposed LTP Implementation Plan 2012/13 – 2014/15 to be submitted to Cabinet in June 2012. The draft pool of schemes together with an indication of those schemes recommended to be awarded direct to SCS, if taken forward, is shown in Appendix C.
2.4The Strategic Commissioning Review approved by the Cabinet in June 2011 proposed that works to be awarded to SCS without tendering should have particular regard to the following criteria: • There are demonstrable skills and capacity available within SCS to deliver the work; • The Council’s control and flexibility can be enhanced by SCS undertaking the work e.g. Urgent works; • SCS still hold ‘Teckal’ compliant status; • Value for money can be demonstrated.
2.5SCS have a proven track record in recent years in delivering the types of schemes detailed in the attached appendices, either through their own direct labour or appointed sub-contractors. SCS are required to demonstrate that individual schemes can be delivered to agreed timescales or the client withholds the right to procure the works via the open market. SCS performance is monitored through agreed Key Performance Indicators and underpinned by monthly Performance Satisfaction Tracking (PST) reviews.
2.6The majority of the schemes listed are programmed in advance to ensure adequate time for effective planning and an even flow of work. Occasionally works are required to be started at short-term notice in order to meet deadlines outside of the Council’s direct control.
2.7To implement this, Cabinet will need to agree that Contract Standing Orders be waived. SCS are currently ‘Teckal’ compliant and are therefore in a position to accept the quantum of work indicated without the Council having to go through the OJEU procedure.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.