CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swindon Borough Council
Cabinet, Wednesday 12 December 2012

Budget Management 2012/13 and Draft Budget 2013/14

Approved Executive 5 papers

Cabinet approved this item on Wednesday 12 December 2012. Below is the council's own wording, with the papers it was decided on.

Item66

Resolved

Resolved – (1) That the Cabinet notes – · the projected in-year General Fund overspend of £773,000; · that officers expect to be able to manage such a level of service overspend from within the Council’s Contingency Fund and one-off resources available to support the 2012/13 Budget, and that there is no requirement to make an allowance in the 2013/14 Budget to replenish General Reserves; · the in-year financial forecasts for the Housing Revenue Account and Dedicated Schools Grant. (2)That the proposed use of £145,000 from Housing Revenue Account reserves to fund Housing improvements, as set out in paragraph 3.15 to 3.18 of the joint report, be approved. (3) That ICT funding of £348,000 from one-off resources be allocated to reduce individual ... view the full minutes text for item 66. (CM: ME)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet, 21 pages

Budget Management 2012-13 and Draft Budget 2013-14 Cabinet Date: 12th December 2012

Authors: Cabinet Member for Finance, and Board Director Finance, Revenues, Benefits and Property Wards: All Locality Affected: All Parishes Affected: All

1. Purpose and Reasons 1.1. This report sets out the latest projected out-turn for 2012-13, the draft Budget proposals for 2013-14 for consultation with residents and stakeholders and the context for the Council’s Medium Term Financial Plan. 1.2. The Council’s Constitution states that the Cabinet will publish initial Budget proposals no later than 2 months before the Budget is adopted. 2. Recommendations In respect of the 2012-13 projected out-turn, Cabinet is requested; 2.1. To note:-

• the projected in-year General Fund overspend of £773k;

• that officers expect to be able to manage such a level of service overspend from within the contingency fund and one-off resources available to support the 2012-13 Budget and that there is no need to make an allowance in the 2013-14 Budget to replenish General Reserves;

• the in-year financial forecasts for the Housing Revenue Account and Dedicated Schools Grant. 2.2. To approve:-

• the proposed drawing of £145k from Housing Revenue Account reserves to fund Housing improvements set out in paragraph 3.15 to 3.188;

• ICT funding of £348k from one-off resources to reduce individual IT workstation costs, delay the need to replace 40% of workstations and allow a Windows 8 upgrade in the next 4 years;

• that, subject to the proposed solution being aligned to the wider ICT strategy, up to £315k of one-off resources be earmarked to fund work being initiated under the Adults Demand Management project to assist service users to access more sustainable forms of support, noting that this platform will then be available to include other services at a later date;

• the proposed virements set out in Appendix 2;

Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Budget Management 2012-13 and Draft Budget 2013-14 Cabinet Date: 12th December 2012

In respect of the 2013-14 Budget, Cabinet is requested; 2.3. To note:-

• the significant amount of uncertainty on the level of funding available for 2013-14, due to the detailed arrangements for the Government’s proposed new funding system for local government not yet having been confirmed;

• the current gap between the assumed funding levels for 2013-14 and the current proposed cost of services set out in Table 5 and that work is continuing to identify further options to close this gap for consideration by Members once actual funding levels are confirmed and before the Final Budget is agreed in February 2013;

• the impact on parish councils of the changes to the annual tax base calculations linked to the forthcoming changes to the Council Tax Support Scheme and the need to liaise with parishes around this issue;

• that the current draft proposals assume a level of contingency of £2m and that Council will need to take a view on the level of contingency it needs to hold to support the 2013-14 Budget in February 2012, based on the advice of the Section 151 Officer at that point;

• that severance payments in line with existing policy will be made to those individuals affected by the Budget proposals and that these will include payments to partner organisations where the payments will result in on- going savings for the Council;

• that the impact on minority groups has been considered for all savings proposals and a full diversity impact assessment has been undertaken where an impact was perceived;

• the work that is progressing on the 2013-14 Budgets for the Housing Revenue Account and the Dedicated Schools Grant. 2.4. To agree:-

• that the draft proposals contained in Appendix 4 to this report are used as the basis for consultation with the Council’s stakeholders;

• the proposed 2013-14 Recreation Charges set out in Appendix 5;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Projected Budget Out-turn 2012-13Appendix 1 4 pages Download
PDF
VirementsAppendix 2 1 pages Download
PDF
and 4: Summary of Proposed Budget Changes 2013-14 and Detailed Budget Proposals 2013-14Appendix 3 8 pages Download
PDF
Proposed Increases in Recreation Fees and ChargesAppendix 5 2 pages Download
PDF
Budget Management 2012/13 and Draft Budget 2013/14Report 21 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. Budget Management 2012/13 and Draft Budget 2013/14This decision
  2. Budget Management UpdateNoted
  3. Budget Management - Outturn 2025/2026Noted
  4. Budget Management UpdateNoted
  5. Budget Management UpdateNoted
  6. Budget Management - Outturn 2024/2025Noted

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies