Resolved – That the Committee: (1) Agrees the response to the Government’s consultation paper as set out in Appendix 2 of the report; (2) Agrees the actions in paragraphs 3.14 and 3.21 of the report to ensure that the Council is actively monitoring its planning performance; and (3) Notes that · 70.6% of major applications in Swindon Borough are decided within 13 weeks, (the proposed Government target being 30%); and · Only 2.7% of major planning application decisions in Swindon Borough over the last two years have been overturned on appeal.
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Planning Performance and the ‘Planning Guarantee’ Planning Committee Date: 15th January 2013
Author: Cabinet Member for Strategic Planning and Sustainability Head of Planning Wards: All Locality Affected: All Parishes Affected: All
1. Purpose and Reasons 1.1 The Government has released a consultation document called “Planning Performance and the Planning Guarantee”. This consultation seeks views on what measures to use to assess each Local Authority’s planning performance, how to performance is measured and a range of related measures to underpin the Government’s “Planning Guarantee”. 1.2 This report seeks to formalise a response to the consultation. The report also details actions that the Council needs to undertake in readiness for the implementation of the Government’s new planning performance regime. 2. Recommendations That Planning Committee: 2.1 Agrees the response to the Government’s consultation paper set out in Appendix 2 of this report; 2.2 Agrees the actions in paras 3.14 and 3.21 of this report to ensure that the Council is actively monitoring its planning performance; and 2.3 Notes that
• 70.6% of major applications in Swindon Borough are decided within 13 weeks, (the proposed Government target being 30%); and • Only 2.7% of major planning application decisions in Swindon Borough over the last two years have been overturned on appeal.
3. Detail 3.1 The ‘Planning Guarantee’ was announced as part of the Government’s Plan for Growth in March 2011 to streamline the planning application process. The ‘Planning Guarantee’ seeks to ensure that no planning application should spend more than 26 weeks with either the Local Planning Authority (LPA) or (in the case of an appeal) the Planning Inspectorate. 3.2 The “Planning Performance and the Planning Guarantee” consultation paper establishes the measures that will support the Planning Guarantee.
Further information on the subject of this report can be obtained from David Dewart, 01793 466445, [email protected]. Planning Performance and the ‘Planning Guarantee’ Planning Committee Date: 15th January 2013
3.3This consultation also links to the proposals contained within the “Growth and Infrastructure Bill” (which is currently going through Parliament), which will introduce legislation to give developers the option of submitting planning applications direct to the Secretary of State where the LPA is deemed to be underperforming. 3.4 To summarise, the Government are seeking views on: 1. The performance criteria by which LPAs may be designated as ‘poorly performing’; 2. The effects of designating an Authority as ‘poorly performing’ on the application process; and 3. The scope of the ‘Planning Guarantee’, which provides that all planning applications should be decided in one year, (with not more than 26 weeks at the LPA and not more than 26 weeks with the Inspectorate if appealed). 3.5 Under the proposals, where an LPA is designated as poorly performing, applicants would have the option to make their application for planning permission direct to the Secretary of State (in practice to the Planning Inspectorate), thereby taking the decision making process away from the Local Authority. 3.6 The mechanism will only apply to applications for planning permission for major development, as defined in the Development Management Procedure Order (residential schemes for ten homes or more or on 0.5 hectares or more, other development involving 1,000 sq m or more or on a site of one hectare or more and minerals and waste schemes) 3.7 Designation will happen annually. An LPA will be designated if it fails at least one of the following two criteria, judged over the previous two years:
• If 30% or fewer of the major development applications it has received have been determined within the statutory period (13 weeks, or 16 weeks if EIA development) (not counting applications governed by planning performance agreements and applications where a time extension has been agreed).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Speaking at Planning CommitteeResolved – To approve the changes to the public speaking protocol as outlined in the report and in the attached docum...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.