Resolved – (1) That the out-turn position for the Revenue Budget for 2012/13, as set out in Table 1 and Appendices 1 and 2 of the joint report, be noted. (2) That the funding “carry-forward” requests, as set out in Table 2, and supported by Corporate Board under the terms set in paragraph 3.4 and in Table 2 of the joint report, be approved. (3) That the Cabinet express its appreciation to all those in the Council’s officer team involved in the delivery of a balanced budget for the 2012/13 Financial Year. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: RH)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Fund Tier 1 Department Tier 2 Service Area Budget Actual Variance Movement Commentary on Reasons for Variance (For the Year) 2012/13 2012/13 since last report £'000 £'000 £'000 £'000
General Chief Executive Stronger Together 100 100 0 0 Fund Internal Audit 428 390 (38) (8) Vacancy saving 528 490 (38) (8) Finance, Revenues, Finance 2,583 2,529 (54) (34) Saving on non-staffing operational expenditure Benefits & Property Revenues & Benefits (1,688) (1,955) (267) (9) Savings on the level of Benefits overpayment made and better than budgeted recovery rates Property Assets (3,371) (4,351) (980) (93) One-off income from property lease surrender and covenant release plus new rental income stream from a newly acquired property. Design & Architecture 2,105 1,904 (201) (95) One-off saving on Office Accommodation insurance costs linked to the rationalisation of buildings and underspends on repairs and maintenance and utilities costs. Corporate (10,122) (9,140) 982 1,218 Adverse variance due to lower than budgeted level of rebate received from SCS. The overall Corporate out-turn position was significantly better than forecast as improvements across the Borough meant that the Council could afford to make an increase in the level of provision for future severance costs from underspends elsewhere within the Borough. This figure is the balancing line within the Council-wide Budget. (10,493) (11,013) (520) 987 Transformation & Strategy & People 1,802 1,852 50 65 Jubilee overspend of £70k partially offset by minor operational savings Strategic Projects Law & Democratic Services 2,858 2,857 (1) (1) Strategic Projects 16 16 0 0 4,676 4,725 49 64 Localities Locality & Partnerships 1,013 973 (40) 0 Underspend after all awards had been made in respect of community grant applications. Communication & Insight 480 452 (28) (1) Underspend on the budget allocated to support the Big Conversation work.
1,493 1,425 (68) (1) Commissioning Management 415 442 27 (2) Improved care pathways and contract management have helped to deliver savings of £284k in mental health care packages. There were also savings from staff vacancies of £115k and Voluntary sector restructuring of £106k. The Children and Adults 58,007 58,669 662 (604) Budget was based on 60 children placements throughout year, however, actual placements exceeded this number and rose as high as 91 during the year. The position improved at the year-end with lower than forecast costs of short-term respite care. Economy / Attainment 6,817 6,648 (169) 13 Commercial Services 43,718 44,381 663 270 Overspends on green waste, highways patching and winter maintenance. 108,957 110,140 1,183 (323) Fund Tier 1 Department Tier 2 Service Area Budget Actual Variance Movement Commentary on Reasons for Variance (For the Year) 2012/13 2012/13 since last report £'000 £'000 £'000 £'000
Service Delivery Children and Families 13,380 13,557 177 (305) Cost pressures exist across the Social Care area teams totalling circa £270k in relation to increased demand for support of children in need and children with no recourse to public funds. Cost pressures of £180k exist in relation to Adoption Services as a result of the total number of adoption related placements made exceeding the budget provision by circa 40% due to a drive to expand this area of service as a lower cost alternative. These cost pressures are offset by a saving of £280k within the Workforce Development Service in relation to reduced uptake of child-minders support services and funding for Higher Education training.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.