Capital Programme 2013/14 Second Quarter 2013/14

Noted Executive 2 papers

Cabinet noted this item on Wednesday 11 December 2013. Below is the council's own wording, with the papers it was decided on.

Item68

Resolved

Resolved – (1) That the 2013/14 Capital Programme position, as set out in paragraphs 3.1 to 3.5 of the joint report, be noted. (2) That the changes to the Council’s Capital Programme as set out in paragraphs 4.1 to 4.6 of the joint report, be approved. (3) That a capital budget of £250,000 be approved to fund the proposal relating to equity share properties as set out in paragraphs 5.1 to 5.7 of the joint report. (4) That the 2013/14 Mid-Year Treasury Management Performance, as set out in paragraphs 6.1 to 6.14 of the joint report, be noted. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: RHu)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet, 9 pages

Capital Programme Monitoring 2nd Quarter 2013/14

Cabinet Date: 11th December 2013

Author: Cabinet Member for Finance Board Director, Resources Wards: All Locality Affected: All Parishes Affected: All

1. Purpose and Reasons 1.1 This report sets out the 2013/14 Capital Programme position as at the end of September 2013 and the mid-year Treasury Management performance for 2013/14. 2. Recommendations Cabinet is recommended to: 2.1 Note the 2013/14 Capital Programme position and mid-year Treasury Management performance; 2.2 Approve the changes to the Capital Programme detailed at paragraphs 4.1 to 4.6 of this report; 2.3 Approve a capital budget of £250,000 to fund the proposal relating to equity share properties as detailed in Section 5 of this report. 3. Detail Capital Programme 2013/14 3.1 The Capital Programme remains aligned around the previous Council structure. However, for the next Cabinet Capital monitoring report the projects will be aligned to the current structure. 3.2 Table 1 below provides a summary of the forecast out-turn position compared with the approved total scheme budgets as at the end of September 2013. Table 1 – Budget Forecasts and variances

Remaining Forecast Variance Budget Spend Group £’000’s £’000’s £’000’s Adult Social Care 922 669 (253) Business Transformation 16,644 16,644 0 Children’s Services 31,216 30,965 (251) Environment & Regeneration & Communities 26,960 26,654 (306)

Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No.463976, or Email [email protected]. Capital Programme Monitoring 2nd Quarter 2013/14

Cabinet Date: 11th December 2013

(E,R&C) Leisure Libraries & Culture 330 330 0 S106 funded schemes 16,640 16,434 (206) GF Services 92,712 91,696 (1,016) Housing Revenue Account (HRA) 32,811 32,811 0 Service Totals 125,523 124,507 (1,016) 3.3 Appendix 1 provides a full scheme by scheme breakdown of variances, but the key ones relate to: 3.3.1. Adult Social Care underspend – £146k saving on equipment costs where the cost is now able to be covered within Revenue and £98k reduced capital spend on extra care sheltered accommodation due to a loan being agreed with Uplands Educational Trust instead of capital spend. 3.3.2. Children’s Services – a number of over and under spends across school schemes, the main variances of which are: Projected underspends of: 3.3.2.1. £300k on Haydonleigh school expansion. Based on current projections and tenders received for the scheme it is anticipated that the full initial budget allocation will not be required. 3.3.2.2. £400k on St Francis 2FE conversion as the scheme is now almost complete. Projected outturn currently shows £400k uncommitted, awaiting final figures from the Diocese project managers to confirm this position. There was a 10% contingency agreed as part of the original budget allocation, currently it is not anticipated that this will be required. Projected overspends of: 3.3.2.3. £250k on Orchid Vale expansion initial figures indicate costs will be higher than estimated due to a combination of factors including initial estimates being based on a scheme delivered 3 years ago and slight revisions to the scope of the project. A more robust budget estimate will be confirmed when tenders are received, and where possible work specification reduced to minimise overspend 3.3.2.4. £170k on Ridgeway School scheme. The initial budget estimate was based on a similar scheme delivered in 2011 for 15 pupils, this scheme will accommodate 20 pupils. Tenders have now been received for the proposed scheme and these have identified that the initial estimate was insufficient. 3.3.3. Environment and Regeneration and Communities (ER&C) - forecast net underspend of £306k which relates to lower than budgeted costs of facilities assistance grants (Disabled Facilities, Private Sector Renewal and Decent Homes Assistance grants) which are all demand led.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Monitoring Forecast DetailsAppendix 1 4 pages Download
PDF
Capital Programme 2013/14 Second Quarter 2013/14Report 9 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 13 attended
DR
Councillor David Renard Leader of the Council and Chair of CabinetChair, present
BM
Councillor Brian Mattock Deputy Leader and Cabinet Member for Health and Adult Social CareVice-Chair, present
RH
Councillor Russell Holland Cabinet Member for FinanceMember, present
MB
Councillor Mike Bawden Cabinet Member for Strategic Projects and TransformationMember, present
FF
Councillor Fionuala Foley Cabinet Member for Children's ServicesMember, present
CE
Councillor Claire Ellis Cabinet Member for Customer Support and Corporate ServicesMember, present
DH
Councillor Dale Heenan Cabinet Member for Strategic Planning and SustainabilityMember, present
RH
Councillor Richard Hurley Cabinet Member for Public Protection, Housing and Streetsmart (Delivery)Member, present
GP
Councillor Garry Perkins Cabinet Member for Economy, Regeneration and CultureMember, present
KW
Councillor Keith Williams Cabinet Member for Highways Strategic Transport and LeisureMember, present
JG
Councillor Jim GrantCabinet Member attendee, in attendance
SP
Councillor Stan PajakCabinet Member attendee, in attendance

All 13 on the meeting page

On this subject at Swindon

Search all
  1. Capital Programme 2013/14 Second Quarter 2013/14This decision
  2. Capital Programme 2026/2027 (Minute for Confirmation)Approved
  3. Capital Programme 2025-2026Approved
  4. Capital Programme 2024/2025 (Minute for Confirmation)Approved
  5. Capital programme 2023-24 (Minute for Confirmation)Approved
  6. Capital Programme to 2026/27 (Minute for Confirmation)Approved

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open