Resolved – (1) That the 2013/14 Capital Programme position, as set out in paragraphs 3.1 to 3.5 of the joint report, be noted. (2) That the changes to the Council’s Capital Programme as set out in paragraphs 4.1 to 4.6 of the joint report, be approved. (3) That a capital budget of £250,000 be approved to fund the proposal relating to equity share properties as set out in paragraphs 5.1 to 5.7 of the joint report. (4) That the 2013/14 Mid-Year Treasury Management Performance, as set out in paragraphs 6.1 to 6.14 of the joint report, be noted. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: RHu)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member for Finance Board Director, Resources Wards: All Locality Affected: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report sets out the 2013/14 Capital Programme position as at the end of September 2013 and the mid-year Treasury Management performance for 2013/14. 2. Recommendations Cabinet is recommended to: 2.1 Note the 2013/14 Capital Programme position and mid-year Treasury Management performance; 2.2 Approve the changes to the Capital Programme detailed at paragraphs 4.1 to 4.6 of this report; 2.3 Approve a capital budget of £250,000 to fund the proposal relating to equity share properties as detailed in Section 5 of this report. 3. Detail Capital Programme 2013/14 3.1 The Capital Programme remains aligned around the previous Council structure. However, for the next Cabinet Capital monitoring report the projects will be aligned to the current structure. 3.2 Table 1 below provides a summary of the forecast out-turn position compared with the approved total scheme budgets as at the end of September 2013. Table 1 – Budget Forecasts and variances
Remaining Forecast Variance Budget Spend Group £’000’s £’000’s £’000’s Adult Social Care 922 669 (253) Business Transformation 16,644 16,644 0 Children’s Services 31,216 30,965 (251) Environment & Regeneration & Communities 26,960 26,654 (306)
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No.463976, or Email [email protected]. Capital Programme Monitoring 2nd Quarter 2013/14
Cabinet Date: 11th December 2013
(E,R&C) Leisure Libraries & Culture 330 330 0 S106 funded schemes 16,640 16,434 (206) GF Services 92,712 91,696 (1,016) Housing Revenue Account (HRA) 32,811 32,811 0 Service Totals 125,523 124,507 (1,016) 3.3 Appendix 1 provides a full scheme by scheme breakdown of variances, but the key ones relate to: 3.3.1. Adult Social Care underspend – £146k saving on equipment costs where the cost is now able to be covered within Revenue and £98k reduced capital spend on extra care sheltered accommodation due to a loan being agreed with Uplands Educational Trust instead of capital spend. 3.3.2. Children’s Services – a number of over and under spends across school schemes, the main variances of which are: Projected underspends of: 3.3.2.1. £300k on Haydonleigh school expansion. Based on current projections and tenders received for the scheme it is anticipated that the full initial budget allocation will not be required. 3.3.2.2. £400k on St Francis 2FE conversion as the scheme is now almost complete. Projected outturn currently shows £400k uncommitted, awaiting final figures from the Diocese project managers to confirm this position. There was a 10% contingency agreed as part of the original budget allocation, currently it is not anticipated that this will be required. Projected overspends of: 3.3.2.3. £250k on Orchid Vale expansion initial figures indicate costs will be higher than estimated due to a combination of factors including initial estimates being based on a scheme delivered 3 years ago and slight revisions to the scope of the project. A more robust budget estimate will be confirmed when tenders are received, and where possible work specification reduced to minimise overspend 3.3.2.4. £170k on Ridgeway School scheme. The initial budget estimate was based on a similar scheme delivered in 2011 for 15 pupils, this scheme will accommodate 20 pupils. Tenders have now been received for the proposed scheme and these have identified that the initial estimate was insufficient. 3.3.3. Environment and Regeneration and Communities (ER&C) - forecast net underspend of £306k which relates to lower than budgeted costs of facilities assistance grants (Disabled Facilities, Private Sector Renewal and Decent Homes Assistance grants) which are all demand led.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.