Local Transport Body Business Case and Scheme Capabilities

Approved Committee 6 papers

Swindon & Wiltshire Local Transport Body approved this item on Wednesday 8 January 2014. Below is the council's own wording, with the papers it was decided on.

Item17

Resolved

Resolved – That the proposed approach (as set out in Appendix 1 to the report) to the development of Outline Business Cases for the prioritised major transport schemes as submitted to the Department for Transport in July 2013, be approved.
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Swindon & Wiltshire Local Transport Body

Commercial Case

Issue Description DfT Recommended Scope of work to be undertaken and scheme progress requirement SWLTB for Outline requirement for Business Outline Business Junction 15 Junction 16 A350 Case Case Introduction Outline the Update from Full Compliance On track On track On track approach taken to strategic BC assess commercial viability.

Output based Summarise the Complete Proportionate On track On track On track specification requirement in Approach Scheme design and Scheme design and Scheme requirements to terms of outcomes build requirements. build requirements. be stated. and outputs.

Procurement Detail procurement Complete Proportionate On track On track On track strategy /purchasing Approach Preferred Preferred procurement Procurement options to be options including procurement approach to be set out. assessed using scoring approach to be set matrix. Preferred option to how they will out. be reported. secure the Procurement options: term economic, social maintenance contractor, and environmental traditional build only, factors outlined in Design & Build. the economic case. Scoring criteria: legal, timescales, cost certainty, risk exposure. Issue Description DfT Recommended Scope of work to be undertaken and scheme progress requirement SWLTB for Outline requirement for Business Outline Business Junction 15 Junction 16 A350 Case Case Sourcing options Explain the options Outline Proportionate On track On track On track for sources of initial Approach Preferred options Preferred options As above, ties into provision of findings considered with considered with procurement strategy. partners. partners. services to meet the business need e.g. partnerships, framework, existing supplier arrangements, with rationale for selecting preferred sourcing option. Issue Description DfT Recommended Scope of work to be undertaken and scheme progress requirement SWLTB for Outline requirement for Business Outline Business Junction 15 Junction 16 A350 Case Case Payment Set out the Outline Full Compliance On track On track On track mechanisms proposed payment initial mechanisms that findings will be negotiated with the providers e.g. linked to performance and availability, providing incentives for alternative revenue streams.

Pricing To include Outline Full Compliance On track On track On track framework and incentives, initial charging deductions and findings mechanisms performance target. Issue Description DfT Recommended Scope of work to be undertaken and scheme progress requirement SWLTB for Outline requirement for Business Outline Business Junction 15 Junction 16 A350 Case Case Risk allocation Present an Outline Proportionate On track On track On track and transfer assessment of how initial Approach Basic statement of Basic statement of Basic statement of the types of risk findings proposals only, based proposals only, based proposals only, based on on preferred on preferred preferred procurement might be procurement procurement approach. approach. apportioned or approach. shared, with risks allocated to the party best placed to manage them subject to achieving value for money.

Contract length Set out scenarios Outline Proportionate On track On track On track for contract length initial Approach Basic statement of Basic statement of Basic statement of (with rationale) findings proposals only. proposals only. proposals only, in line with standard Wiltshire Council and proposed key procurement / payment contractual approach. clauses. Issue Description DfT Recommended Scope of work to be undertaken and scheme progress requirement SWLTB for Outline requirement for Business Outline Business Junction 15 Junction 16 A350 Case Case Human resource Personnel/people N/A N/A N/A N/A issues management/trade union implications, where applicable, including TUPE regulations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Commercial Case_(v2) 131219Report 38 KB DownloadRead as text
PDF
Economic Case progress_(v2) 131219Report 56 KB Download
PDF
Financial Case progress_(v2) 131219Report 38 KB Download
PDF
Local Transport Body Business Case and Scheme CapabilitiesReport 42 KB Download
PDF
Management Case progress_(v2) 131219Report 43 KB Download
PDF
Strategic Case progress_(v2) 131219Report 43 KB Download

At this meeting

Whole meeting
16MinutesOn the agenda
17Local Transport Body Business Case and Scheme CapabilitiesThis decision
18Strategic Economic Plan/Transport 2025 Vision (for information only) (to follow)Decided

On this subject at Swindon

Search all
  1. Local Transport Body Business Case and Scheme CapabilitiesThis decision
  2. Local Transport Plan Annual Implementation Plan 2026/2027Approved
  3. Local Transport Plan Annual Implementation Plan 2025/2026Approved
  4. Local Transport Plan Annual Implementation Plan 2024/2025Approved
  5. Local Transport Plan Annual Implementation Plan 2023/24Approved
  6. Local Transport Plan Implementation Plan 2022-2023Approved

More from Swindon Swindon & Wiltshire Local Transport Body

All decisions
MeetingDecisionOutcome
1 May 2015 Ratification of MinutesResolved – (1) That the minutes of the meeting held on 29 th October 2014 be accepted as a correct record. (2) That t... Decided Open
21 Apr 2015 A350 Yarnbrook and West Ashton Relief Road Outline Business CaseResolved – That had the SWLTB been in a position to do so, it would have: (1) Approved the Outline Business Case for ... Approved Open
21 Apr 2015 A350 Chippenham Bypass Improvements (Bumpers Farm) Full Business CaseResolved – That had the SWLTB been in a position to do so, it would have: (1) Approved the Full Business Case for the... Approved Open
29 Oct 2014 Major Transport Schemes - UpdatesResolved – That this Transport Body: (1) Approves the Outline Business Case (OBC) for the M4 J16 Improvement scheme; ... Approved Open
17 Jul 2014 Appointment of ChairResolved – That Councillor Fleur de-Rhe Philipe be appointed Chair of this Transport Body for the Municipal Year 2014... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies