Capital Programme 2014/15 to 2016/17 (Minute for Confirmation)

Approved Executive 5 papers

Cabinet approved this item on Wednesday 5 February 2014. Below is the council's own wording, with the papers it was decided on.

Item86

Resolved

Resolved –( 1) That the Council be recommended to approve - · an overall budget of £8.680m for the Children’s Services capital schemes identified in Appendix 1 of the joint report as 2014/2015 starts for approval; · a total budget of £12.142m for the 2014/15 Highways capital schemes detailed at Appendix 2 of the joint report; · a total budget of £6.515m for the 2014/15 Assets and Property capital schemes detailed at Appendix 3 of the joint report and highlighted “For Approval”. (2) That the Council note the Council’s future capital requirements as detailed in Appendices 1, 2 and 3 of the joint report. The reasons for the decision and alternative options are as set out in the report to the meeting.
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet

Capital Programme 2014/15 to 2016/17

Cabinet Date: 5th February 2014

Author: Cabinet Member for Finance Board Director, Resources Wards: All Locality Affected: All Parishes Affected: All

1. Purpose and Reasons 1.1 To report new Capital Programme requirements for the period 2014-15 to 2016- 17 and beyond. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 2. Recommendations Cabinet is recommended to ask Council to: 2.1 Approve an overall budget of £8.680m for the Children’s Services capital schemes identified at Appendix 1 as “2014-2015 starts for approval,” 2.2 Approve a total budget of £12.142m for the 2014-15 Highways capital schemes detailed at Appendix 2, 2.3 Approve a total budget of £6.515m for the 2014-15 Assets and Property capital schemes detailed at Appendix 3 and highlighted “For Approval,” 2.4 Approve a total budget requirement of £580k for Older Peoples capital schemes detailed at Appendix 4, 2.5 Note the future capital requirements as detailed in Appendices 1, 2 and 3. 3. Detail Capital Programme 3.1 The Council approved, on Cabinet’s recommendation, a full three-year Capital Programme in February 2011, covering the period from 2011-12 through to 2013- 14 (Council Minute 115, 2010/11 refers). This programme included the main funding settlements for schools and highways. 3.2 This report details the Capital Programme requirements for 2014/15, which require approval, and indicative requirements beyond 2014/15. As grant funding notification for the period from 2014/15 to 2016/17 has not been provided, officers are recommending that approval for new 2014/15 starts only are given at

Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No.463976, or Email [email protected]. Capital Programme 2014/15 to 2016/17

Cabinet Date: 5th February 2014

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Childrens Capital SchemesAppendix 1 19 KB Download
PDF
Highways Capital SchemesAppendix 2 19 KB Download
PDF
Property and Assets Capital SchemesAppendix 3 16 KB Download
PDF
Older Peoples Capital SchemesAppendix 4 15 KB Download
PDF
Capital Programme 2014/15 to 2016/17 (Minute for Confirmation)Report 38 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. Capital Programme 2014/15 to 2016/17 (Minute for Confirmation)This decision
  2. Capital Programme 2026/2027 (Minute for Confirmation)Approved
  3. Capital Programme 2025-2026Approved
  4. Capital Programme 2024/2025 (Minute for Confirmation)Approved
  5. Capital programme 2023-24 (Minute for Confirmation)Approved
  6. Capital Programme to 2026/27 (Minute for Confirmation)Approved

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies