Resolved – (1) That the update on construction progress for the primary school at Tadpole Farm, Swindon, be noted. (2) That the use of the Red House Community Centre site from September 2014 as a temporary provision for the Tadpole Farm Primary School pending the completion of the construction of that school, be approved. (3) That a budget of £852,551 for the construction of the Red House Community Centre, be approved to be funded from monies from Haydon 3 Section106 Planning Agreements provisionally earmarked as social contributions in the report to the Cabinet dated 19th January 2011. (4) That the Cabinet Member for Strategic Projects and Transformation, in consultation with the local Ward Councillors, submit a further report to the Cabinet at or before its September 2014 meeting, on the future use of Red House Community Centre site once pupils have relocated to the permanent school site at Tadpole Farm. The reasons for the decision and ... view the full minutes text for item 104. (CM: RHu)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Tadpole Farm Primary School – Temporary Provision Cabinet Date: 19th March 2014
Author: Cabinet Member for Children’s Services Board Director, Commissioning/ Head of Commissioning – Economy and Attainment Wards: St Andrews Locality Affected: North Parishes Affected: Blunsdon St Andrew
1. Purpose and Reasons 1.1 This report provides an update on construction progress associated with the proposed Tadpole Farm Primary School which was due to open in September 2014 and the delay experienced in its construction. The implication of the delay is that the Council will need to make a temporary provision elsewhere to ensure that adequate school places are created for September 2014. 1.2 Providing sufficient, quality school places supports the Council’s strategic objective of “right skills, right jobs in the right places.” 2. Cabinet is recommended to: 2.1 Note the update on construction progress for the primary school at Tadpole Farm. 2.2 Approve the use of the Red House Community Centre from September 2014, as a temporary provision pending the construction of the Tadpole Farm Primary School. 2.3 Approve a budget of £852,551 for the construction of the Red House Community Centre, to be funded from monies from Haydon 3 s106 Agreements provisionally earmarked as social contributions in the report to Cabinet dated 19th January 2011. 2.4 Request that the Cabinet Member for Strategic Projects and Transformation, in consultation with the local Ward Councillors, bring a further report to Cabinet on the future use of Red House Community Centre once pupils have relocated to the permanent site at Tadpole Farm. 3. Detail 3.1 At its meeting on 20th March 2013, the Cabinet approved the location for a new primary school on the Tadpole Lane development from September 2014 (Cabinet Minute 117 2012/13 refers). The relevant risks and inter dependencies involved in the project were highlighted in the relevant Cabinet report.
Further information on the subject of this report can be obtained from Paddy Bradley, Head of Commissioning – Economy and Attainment, Direct Dial 01793 465744, [email protected]. Tadpole Farm Primary School – Temporary Provision Cabinet Date: 19th March 2014
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.