Resolved – (1) That the Cabinet notes the Projected Out-turn by Service 2014/15, as set out in Table 1 and Appendices 1 and 2 to the joint report. (2) That the proposed budget virements , as set out in Appendix 3 to the joint report, be approved. (3) That a loan of £280,000 be made to Swindon Commercial Services Ltd to finance the purchase and installation of a can baler for its Recycling facility as referred to in paragraph 6 of the joint report. (4) That the maximum limit of the cashflow loan facility to Swindon Commercial Services Ltd be reduced from £2.25m to £1.25m as referred to in paragraph 6 of the joint report. (5) That the sum of £88,000 be approved for the deep clean and seal of surfacing in Swindon Town Centre, as referred to in paragraph 7 of the joint report, to be funded from one-off resources. (6) That the Council be recommended that – (a) the Board Director, Resources be authorised to (i) submit applications for external funding which would further the Council’s strategic objectives, and (ii) accept the award of external funding which further the Council’s strategic objectives, in consultation with the relevant Cabinet Member, (b) the Director of Law and Democratic Services be authorised to amend the Scheme of Delegation accordingly. (7) That the proposed work to be undertaken on a detailed needs assessment of the Library service following recent consultation feedback associated with the preparation of a revised Library Strategy, as referred to in paragraph 9 of the joint report, be noted. The reasons for the decision and alternative options are as set out in this minute and the report to the meeting. (CM: RH)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Budget Management 2014-15 Cabinet Date: 23rd July 2014
Authors: Cabinet Member for Finance, and Board Director, Resources Wards: All Locality Affected: All Parishes Affected: All
1. Purpose and Reasons 1.1. This report presents the 2014-15 Revenue forecast out-turn at the end of May 2014. 1.2. The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 1.3. Responsible budget management underpins the Council’s Strategic Objective of consistently making the best use of all available resources as well as providing focus for the Change Programmes. 2. Recommendations Cabinet is recommended to: 2.1. Note the projected out-turn position for 2014-15 set out in Table 1 and Appendices 1 and 2; 2.2. Approve the virements set out in Appendix 3; 2.3. Approve the loan of £280k to Swindon Commercial Services Ltd to finance the can baler purchase and installation; 2.4. Approve the reduction in the maximum limit of the cashflow loan facility to Swindon Commercial Services Ltd from £2.25m to £1.25m; 2.5. Approve the sum of £88k for the deep clean and seal of surfacing in the Town Centre, to be funded from one-off resources; 2.6. Recommend to Council that (a) the Board Director, Resources be authorised to (i) submit applications for external funding which would further the Council’s strategic objectives, and (ii) accept the award of external funding which further the Council’s strategic objectives, in consultation with the relevant Cabinet Member,
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Budget Management 2014-15 Cabinet Date: 23rd July 2014
(b) the Director of Law and Democratic Services be authorised to amend the Scheme of Delegation accordingly; 2.7. Note the proposed work to be undertaken on a detailed needs assessment of the Library service following recent consultation feedback. 3. 2014-15 Projected Out-turn 3.1. The only firm projected variance at this early stage in the financial year is a shortfall in rental income within the Council’s commercial property portfolio. Although a number of risks within service areas are emerging, it is expected that the recently adopted strategy of early delivery of future year savings will continue as part of the mitigation. In this context, it is to be expected that the Council will deliver services within the overall cash limit for 2014-15. 3.2. The budget and projected out-turn by each Department is set out in Table 1 below and a more detailed analysis is set out in Appendices 1 and 2. Table 1 – Projected Out-turn By Department
Department Budget Full-Year Projected 2014/15 Projected Variance Out-turn £'000 £'000 £'000 Chief Executive (2,219) (2,119) 100 Resources 2,751 2,751 0 Corporate (14,622) (14,622) 0 Commissioning 98,832 98,832 0 Service Delivery 57,926 57,926 0 Total General Fund 142,668 142,768 100
4. Department Summaries and Explanation of Key issues Chief Executive 4.1. The Chief Executive’s Department is currently projecting an overspend of £100k due to vacant commercial properties. A risk in relation to these vacant properties was identified in the 2014-15 Budget report but no base budget savings were identified to mitigate this on the basis that work would be undertaken to let the properties in 2014-15; this work is underway. In addition, the Property Assets team has previously been successful in securing non- recurring property related income. To date one-off income has been received from a covenant release, a successful legal claim for overpaid rent on Premier House and the recovery of dilapidations, which are mitigating the full effects from the pressure on rental income.
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Budget Management 2014-15 Cabinet Date: 23rd July 2014
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.