Resolved – (1) That the Capital Programme position and mid-year Treasury Management performance for 2014/15 , as set out in the joint report, be noted. (2) That the changes to the Council’s Capital Programme, as set out in paragraph 3.5 of the joint report, be approved. (3) That the Stage 1 Heritage Lottery Fund Grant Application for a new Swindon Museum and Art Gallery, as detailed in paragraphs 3.6 to 3.9 of the joint report, be endorsed. (4) That the current pressures and timescale for 2015/16 Capital Programme approvals, as detailed in paragraphs 3.10 to 3.13 of the joint report, be noted. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: BF)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Capital Programme Monitoring 2nd Quarter and Mid-Year Treasury Performance 2014/15 Cabinet Date: 10th December 2014
Author: Cabinet Member for Finance Board Director, Resources Wards: All Locality Affected: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report sets out the 2014/15 Capital Programme position as at the end of September 2014 and the mid-year Treasury Management performance for 2014/15. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 2. Recommendations Cabinet is recommended to: 2.1 Note the 2014/15 Capital Programme position and mid-year Treasury Management performance. 2.2 Approve the changes to the Capital Programme detailed at paragraph 3.5. 2.3 Endorse the Stage 1 Heritage Lottery Fund grant application for a new Museum and Art Gallery, as detailed in paragraphs 3.6 to 3.9 of the report 2.4 Note the current pressures and timescale for 2015/16 approvals as detailed in paragraphs 3.10 to 3.13 of the report 3. Detail Capital Programme 2014/15 3.1 Table 1 below provides a summary of the forecast out-turn position compared with the approved total scheme budgets, as at the end of September 2014. The projected out-turn position represents the expected total spend for the scheme to completion over all remaining years.
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No.463976, or Email [email protected]. Capital Programme Monitoring 2nd Quarter and Mid-Year Treasury Performance 2014/15 Cabinet Date: 10th December 2014
Table 1 – Budget Forecasts and Variances Remaining Forecast 14/15 Budget Spend to Spend Variance 14/15 completion to Date Group £’000’s £’000’s £’000’s £’000’s Schools 35,146 34,756 8,343 (390) Social Care 2,743 2,743 81 0 Community Works 8,225 8,225 1,283 0 Corporate Projects 24,561 23,985 10,368 (576) Transport 17,152 16,929 2,726 (223) S106 funded projects 18,745 18,745 510 0 GF Services 106,572 105,383 23,311 (1,189) Housing Revenue Account 31,651 31,651 3,464 0 (HRA) Service Totals 138,223 137,034 26,775 (1,189)
3.2Appendix 1 provides a full scheme by scheme breakdown of variances by project, but the key ones relate to: 3.2.1 Savings across several school projects that have been completed under budget:
• £45k relating to the scheme at Red Oaks Primary School, • £476k relating to the scheme at St Francis Primary School, • £31k relating to the scheme at Orchid Vale Primary School, • £20k relating to the scheme at Rodbourne Cheney Primary School, • £41k relating to the scheme at The Ridgeway School, and • £34k relating to the redesign works at Haydonleigh Primary School. 3.2.2 Over spend across several school projects:
• £200k for additional external works due to an increase in the scope of ground and external works at Even Swindon Primary School, • £47k for additional works at The Chalet School. These works had to be completed over the Christmas period which incurred additional cost, and adverse weather and ground conditions also contributed to further cost increases, and • £10k due to some additional roof works required at Commonweal School.
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No.463976, or Email [email protected]. Capital Programme Monitoring 2nd Quarter and Mid-Year Treasury Performance 2014/15 Cabinet Date: 10th December 2014
3.3Savings across several Corporate projects that are forecasting coming in under budget are highlighted below: 3.3.1 Various net savings projected across a number of Wichelstowe capital contracts, 3.3.2 Disabled Facilities Grant which is demand led and not anticipated to be fully spent, and 3.3.3 Savings of £223k relating to work at Davis Place Car Park, which is not proceeding. 3.4 Table 2 below shows how the current approved programme identified at Table 1 is being funded: Table 2: Capital Programme funding
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.