Resolved – (1) That the Capital Programme Out-turn position for 2014/15 , as set out in the joint report, be noted. (2) That the changes to the Council’s Capital Programme, as set out in paragraph 3.4 to 3.8 of the joint report, be approved. (3) That the Treasury Management performance 2014/15, as detailed in paragraphs 4.1 to 4.12 and the Prudential Indicators as set out in Appendix 2 to the joint report, be noted . The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: BM)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Capital Programme Monitoring Outturn and Treasury Performance 2014/15 Cabinet Date: 17th June 2015
Author: Cabinet Member for Finance, People and Performance Board Director, Resources Wards: All Locality Affected: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report sets out the 2014/15 Capital Programme position as at the end of March 2015 and the Treasury Management performance for 2014/15. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 2. Recommendations Cabinet is recommended to: 2.1 Note the latest 2014/15 Capital Programme position as at financial year end. 2.2 Approve the changes to the Capital Programme detailed in paragraphs 3.4 to 3.8. 2.3 Note the 2014/15 Treasury Management performance as detailed at paragraphs 4.1 to 4.12 and Prudential Indicators shown at Appendix 2. 3. Detail Capital Programme 2014/15 3.1 Table 1 below provides a summary of the forecast out-turn position compared with the approved total scheme budgets, as at the end of March 2015. The projected out-turn position represents the expected total spend for the scheme to completion over all remaining years and includes schemes for 2015/16 approved at February Cabinet.
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No.463976, or Email [email protected]. Capital Programme Monitoring Outturn and Treasury Performance 2014/15 Cabinet Date: 17th June 2015
Table 1 – Budget Forecasts and Variances
Remaining Forecast 14/15 Forecast Budget Spend to Spend Variance 14/15 completion to Date Group £’000’s £’000’s £’000’s £’000’s Community Works 8,112 8,112 3,738 0 Corporate Projects 26,589 26,323 14,934 (266) S106 19,240 19,240 4,995 0 Schools 35,297 34,865 18,395 (432) Social Care 2,743 2,631 919 (112) Transport 17,422 17,185 8,490 (237) GF Services 109,403 108,356 51,471 (1,047) Housing Revenue Account (HRA) 31,651 31,561 12,658 (90) Service Totals 141,054 139,916 64,128 (1,137) 3.2 Appendix 1 provides a full scheme by scheme breakdown of variances by project, but the key ones relate to: 3.2.1 Savings across several school projects that have been completed under budget:
• £50k relating to the scheme at Red Oaks Primary School.
• £520k relating to the scheme at St Francis Primary School.
• £20k relating to the scheme at Rodbourne Cheney Primary School.
• £41k relating to the scheme at The Ridgeway School.
• £55k relating to the redesign works at Haydonleigh Primary School.
• £32k relating to additional places at Orchid Vale Primary School 3.2.2 Over spend across several school projects:
• £200k for additional external works due to re-measurement of ground works & external works at Even Swindon Primary School.
• £30k for additional works at The Chalet School. These works had to be completed over the Christmas period which incurred additional cost, and adverse weather and ground conditions also contributed to further cost increases.
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No.463976, or Email [email protected]. Capital Programme Monitoring Outturn and Treasury Performance 2014/15 Cabinet Date: 17th June 2015
• £25k due to some additional roof works required at Commonweal School.
• £33k to install Fire Doors at Ridgeway School. 3.2.3 Savings across several Corporate projects that are forecasting coming in under budget:
• Disabled Facilities Grant which is demand led and not anticipated to be fully spent, and carried forward to 2015/16 Budget.
• Savings of £227k relating to Davis Place Car Park, which is not proceeding.
• Savings of £112k relating to non-delivery of Extra Care Projects.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.