Resolved – (1) That the Capital Programme position and mid-year Treasury Management performance for 2015/16 , as set out in the joint report, be noted. (2) That the issues affecting the Council’s Capital Programme, as set out in paragraph 3.2 of the joint report, be noted. (3) That the additions to the Council’s Capital Programme, as set out in paragraph 3.3 of the joint report, be approved. (4) That the changes to the Council’s Capital Programme, as set out in paragraph 3.4 of the joint report, be noted. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: FF)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Capital Programme Monitoring Q2 and Mid-Year Treasury Performance 2015-16 Cabinet Date: 9th December 2015
Author: Cabinet Member for Finance, People and Performance Board Director, Resources Wards: All Locality Affected: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report sets out the 2015/16 Capital Programme position as at the end of September 2015 and the mid-year Treasury Management performance for 2015/16. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 2. Recommendations Cabinet is recommended to: 2.1 Note the latest 2015/16 Capital Programme position and mid-year Treasury Management performance; 2.2 Note the positions on the schemes detailed at paragraph 3.2; 2.3 Approve the additions to the Capital Programme detailed in paragraph 3.3; 2.4 Note the changes to the Capital Programme detailed in paragraph 3.4. 3. Detail Capital Programme 2015/16 3.1 Table 1 below provides a summary of the forecast out-turn position of the Capital Programme compared with the remaining scheme budgets, as at the start of the financial year. The projected out-turn position represents the expected total spend for the scheme to completion over all remaining years.
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No.463976, or Email [email protected]. Capital Programme Monitoring Q2 and Mid-Year Treasury Performance 2015-16 Cabinet Date: 9th December 2015
Table 1 – Budget Forecasts and Variances
Remaining Forecast Forecast Budget Spend to Variance 15/16 completion Group £000s £000s £000s Community Works 4,345 4,194 (151) Corporate Projects 34,217 34,297 80 Section 106 (S106) 13,596 15,289 1,693 Schools 18,490 18,591 101 Social Care 2,692 2,692 0 Transport 15,481 15,481 0 GF Services 88,821 90,544 1,723 Housing Revenue Account (HRA) 36,548 36,548 0 Service Totals 125,369 127,092 1,723 3.2 Appendix 1 provides a full scheme-by-scheme breakdown of variances by project. There are a number of issues with current schemes that Cabinet is asked to note: 3.2.1 Savings across Community Works for the replacement of cremators completed under budget. 3.2.2 Overspend for the Thamesdown Transport Project (purchase of Thamesdown Transport Depot) is for stamp duty costs that were not included in the budget approval. 3.2.3 Savings of £50k have been achieved on the scheme at Haydon Leigh School – the saving is as a result of negotiations with the contractor around the settlement of the final account to reflect the value engineering undertaken during the construction process. 3.2.4 An overspend of £152k relating to the refurbishment at Crowdy’s Hill School – part of the new buildings were changed to accommodate Sport England requirements which resulted in additional ground works being required to provide the necessary foundations for the school. Changes to the Programme 3.3 Cabinet is asked to approve the following changes to the programme: 3.3.1 A budget of 58k for Angel Ridge public open space and play area funded from S106 contributions. The S106 contributions have been received
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No.463976, or Email [email protected]. Capital Programme Monitoring Q2 and Mid-Year Treasury Performance 2015-16 Cabinet Date: 9th December 2015
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.