Resolved – (1) That the latest 2015/16 Capital Programme position be noted. (2) That the positions on the schemes detailed in paragraph 3.2 of the report be noted. (3) That the additions to the Capital Programme, detailed in paragraph 3.3 of the report, be approved. (4) That the changes to the Disabled Facilities Grant, detailed in paragraph 3.4 of the report, be noted. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: RH)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Capital Programme Monitoring 3rd Quarter 2015-16 Cabinet Date: 16th March 2016
Author: Cabinet Member for Finance, People and Performance Board Director, Resources Wards: All Locality Affected: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report sets out the 2015/16 Capital Programme position as at the end of December 2015. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 2. Recommendations Cabinet is recommended to: 2.1 Note the latest 2015/16 Capital Programme position; 2.2 Note the positions on the schemes detailed at paragraph 3.2; 2.3 Approve the additions to the Capital Programme detailed in paragraph 3.3; 2.4 Note the changes to the Disabled Facilities Grant detailed in paragraph 3.4. 3. Detail Capital Programme 2015/16 3.1 Table 1 below provides a summary of the forecast out-turn position of the Capital Programme compared with the remaining scheme budgets, as at the start of the financial year. The projected out-turn position represents the expected total expenditure for the scheme to completion over all remaining years.
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No.464384, or Email [email protected]. Capital Programme Monitoring 3rd Quarter 2015-16 Cabinet Date: 16th March 2016
Table 1 – Budget Forecasts and Variances
Remaining Forecast Forecast Budget Spend to Variance 15/16 completion Group £000s £000s £000s Community Works 4,285 4,134 (150) Corporate Projects 40,973 41,053 80 Section 106 (S106) 13,822 13,822 0 Schools 19,280 19,382 102 Social Care 2,154 2,154 0 Transport 19,351 19,351 0 GF Services 99,865 99,896 31 Housing Revenue Account (HRA) 36,982 36,982 0 Service Totals 136,847 136,878 31
3.2Appendix 1 provides a full scheme-by-scheme breakdown of variances by project. There are a number of issues with current schemes that Cabinet is asked to note also that the following have been reported to Cabinet for the 2nd Quarter and have not changed: 3.2.1 Savings of £150k have been achieved for the replacement of cremators completed under budget. (Appendix 1 Line No. 4) 3.2.2 Overspend for the Thamesdown Transport Project (purchase of Thamesdown Transport Depot) is for stamp duty costs that were not included in the budget approval. (Appendix 1 Line No. 42) 3.2.3 An overspend of £152k relating to the refurbishment at Crowdy’s Hill School – part of the new buildings were changed to accommodate Sport England requirements which resulted in additional ground works being required to provide the necessary foundations for the school. (Appendix 1 Line No. 129) 3.2.4 Savings of £50k have been achieved on the scheme at Haydon Leigh School – the saving is as a result of negotiations with the contractor around the settlement of the final account to reflect the value engineering undertaken during the construction process. (Appendix 1 Line No. 135) Changes to the Programme 3.3 Cabinet is asked to approve the following changes to the programme:
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No.464384, or Email [email protected]. Capital Programme Monitoring 3rd Quarter 2015-16 Cabinet Date: 16th March 2016
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.