CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swindon Borough Council
Cabinet, Wednesday 7 December 2016

Capital Monitoring Quarter 2 2016-17

Noted Executive 2 papers

Cabinet noted this item on Wednesday 7 December 2016. Below is the council's own wording, with the papers it was decided on.

Item71

Resolved

Resolved – (1) That the forecast capital expenditure, set out in Tables 1 and 2 and Appendix 1 to the report, be noted. (2) That the release of £100k to Swindon Museum and Art Gallery Trust (paragraph 3.3.4 to 3.3.7) be agreed. (3) That the Corporate Director for Economy, Regeneration & Skills be authorised to agree, with the Swindon Museum and Art Gallery Trust Director and Chief Executive, the staging and mechanism of payments provided for the next stage of the development. (4) That the changes to the programme, set out in section 3.3, be agreed. (5) That the distribution of £300,520 of Devolved Formula Capital to Local Authority maintained schools be agreed. (6) That the contents of Tables 3 – 6 in the report, regarding the 2015-16 Community Infrastructure Levy, be noted and that these be published on the Council’s website. (7) That the annual retention of 5% of the total annual Community Infrastructure Levy receipts to cover administration costs, as per paragraph 3.10 of the report, be approved. (8) That the distribution of the non-parished Community Infrastructure Levy Neighbourhood Proportion to the new parishes as if they had existed at the date of the receipt be approved. (9) That the intention for Community Infrastructure Levy receipts to support capital programme proposals to be submitted to Cabinet in February 2017 as part of the annual capital budget setting process, be noted. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM:RH)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet, 9 pages

Capital Monitoring Quarter 2 2016-17 Cabinet Date: 7th December 2016

Authors: Cabinet Member for Finance and Corporate Services and Interim Corporate Director, Resources Wards: All Locality Affected: All Parishes Affected: All

1. Purpose and Reasons 1.1 This report presents the second quarter’s monitoring position for the capital programme and some proposed changes to the Council’s capital programme. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 1.3 Responsible budget management underpins the Council’s strategic objective of consistently making the best use of all available resources as well as providing focus for its change programmes. 2. Recommendations Cabinet is recommended to: 2.1 Note the forecast capital expenditure set out in Table 1 & 2 and Appendix 1, 2.2 Agree to the release of £100k to Swindon Museum and Art Gallery Trust (para. 3.3.4 to 3.3.7 2.3 Authorise the Interim Corporate Director for Economy, Regeneration & Skills to agree, with the Swindon Museum and Art Gallery Trust Director/Chief Executive, the staging and mechanism of payments provided for the next stage of the development. 2.4 Approve the changes to the programme in section 3.3. 2.5 Agree to the distribution of £300,520 of Devolved Formula Capital to Local Authority (“LA”) maintained schools. 2.6 Note the contents of Tables 3 - 6 regarding the 2015-16 Community Infrastructure Levy (CIL) and to approve that these be published on our website. 2.7 Approve the annual retention of 5% of the total annual CIL receipts to cover administration costs per paragraph 3.10 below 2.8 Approve the distribution of the non-parished CIL Neighbourhood Proportion to the new parishes as if they had existed at the date of the receipt.

Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. 464384 or Email [email protected] Capital Monitoring Quarter 2 2016-17 Cabinet Date: 7th December 2016

2.9Note the intention for CIL receipts to support capital programme proposals that will be taken to Cabinet in February 2017 as part of the annual capital budget setting process. 3. Detail Capital Programme – 2016/17 monitoring 3.1 Table 1 below shows the current status of the 2016-17 capital budget and forecast outturn position. The significant budget movements are detailed in paragraph 3.3.1 - 3.3.3 below. Table 2 shows how the capital programme is being funded.

Table 1 - Budget Forecasts and Variances Service Approved Forecast Projected Budget Scheme Variance 2016-17 Spend to Onwards Completion Group £’000’s £’000’s £’000’s Community Works 1,903 1,903 0 Corporate Projects 37,961 40,824 2,864 Section 106 10,413 10,413 0 Schools 15,431 12,112 -3,319 Social Care 2,329 2,329 0 Transport 57,984 58,069 85 Total General Fund 126,021 125,650 -371 HRA 35,129 35,129 0 Service Totals 161,150 160,779 -371

Table 2 - Capital Programme funding Current Funding Requirement Expenditure £'000 Budget 161,150 Balance to be financed: 161,150 Capital Receipts 3,308 Section 106 Deposits 23,654 Grant Funding 75,432 Revenue Contributions 3,082 HRA balances 33,602 Increase in Borrowing Requirement 22,072 Total 161,150

3.2The detailed capital monitoring for quarter 2 is attached at Appendix 1.

Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. 464384 or Email [email protected] Capital Monitoring Quarter 2 2016-17 Cabinet Date: 7th December 2016

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Budget Monitoring 2016-17 SchemesAppendix 1 8 pages Download
PDF
Capital Monitoring Quarter 2 2016-17Report 9 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. Capital Monitoring Quarter 2 2016-17This decision
  2. Capital Monitoring – Quarter 1 2026/2027Noted
  3. Capital Monitoring - Out-turn 2025-2026Noted
  4. Capital Monitoring - Quarter 3 2025/2026Noted
  5. Capital Monitoring Outturn 2024-2025Noted
  6. Capital Monitoring - Quarter 3 2024/2025Noted

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies