Resolved – (1) That the projected Revenue Budget out-turn position for 2016/17, set out in Table 1 and Appendix 1 to the report, be noted. (2) That the virements set out in Appendix 2 to the report be approved. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM:RH)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Budget Management 2016/17 Cabinet Date: 15th March 2017
Authors: Cabinet Member for Finance and Corporate Services, and Interim Corporate Director Resources Wards: All Locality Affected: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report presents the 2016/17 Revenue Budget forecast out-turn at the end of January 2017. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 1.3 Responsible budget management underpins the Council’s strategic objective of consistently making the best use of all available resources as well as providing focus for the Council’s transformation programme. 2. Recommendations Cabinet is recommended to: 2.1 Note the projected Revenue Budget out-turn position for 2016/17 set out in Table 1 and Appendix 1; and 2.2 Approve the virements set out in Appendix 2. 3. Detail 2016/17 Projected Out-turn 3.1 The projected budget out-turn as at the end of January 2017 is an overspend of £6.263m, an improvement of £245k from the previous month. 3.2 The significant changes since the last report to Cabinet are : 3.2.1 An improvement in the forecast for corporate budgets of £137k reflecting a revenue payment from Thamesdown Transport and a repayment of service financing costs, partly offset by the write-off of Seqol debt that was reported to Cabinet in December 2016; 3.2.2 Savings in Children’s Services due to the application of additional funding of £99k to support children in external placements; 3.2.3 An improved forecast on parking of £67k, reflecting lower operating costs and increased income;
Further information on the subject of this report can be obtained from Mick Bowden on Direct Dial No. [phone removed] or Email [email protected] Budget Management 2016/17 Cabinet Date: 15th March 2017
3.2.4 A reduction in anticipated planning fee income of £120k 3.3 Previous reports to Cabinet have set out the approach to meeting the pressures in the current financial year, through the revision of the Council’s approach to providing for the repayment of debt and the use of one-off earmarked reserves. Throughout the financial year the biggest financial risk facing the council has been the delivery of savings in adult social care and the current forecast assumes that £0.4m of adult social care savings will be delivered in the last two months of 2016/17. 3.4 The projected overspend within Streetsmart (£3m) is predominantly due to the increased gate fee for waste disposal, as reported to Cabinet on 13 July 2016. The Council had previously paid waste disposal costs below the market rate as a result of the profit made by PPS Ltd on solar schemes. This was affected by changes in solar tariffs by Central Government and therefore higher gate fees, closer to market levels, were agreed with effect from 1 April 2016. 3.5 The budget and projected out-turn by Department is set out in Table 1 below, with a more detailed analysis is set out in Appendix 1. Table 1 – Projected Out-turn By Department
Department Budget Full-Year Projected Movement 2016/17 Projected Variance since last Outturn report £'000 £'000 £'000 £'000 Adult Services 72,594 77,256 4,662 23 Children Services 26,391 28,200 1,809 (116) Communities and Place 28,137 32,137 4,000 (83) Economy (871) (638) 233 127 Chief Executive 4,226 4,143 (83) (3) Resources 20,037 18,918 (1,119) (56) Corporate (15,288) (18,527) (3,239) (137) Total General Fund 135,226 141,489 6,263 (245)
Virements 3.6 Since the last report, there have been some minor virements to reflect changes to the allocation of costs between departments. Members are asked to agree these virements as set out in Appendix 2.
Further information on the subject of this report can be obtained from Mick Bowden on Direct Dial No. [phone removed] or Email [email protected] Budget Management 2016/17 Cabinet Date: 15th March 2017
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.