Resolved – (1) That the projected Revenue Budget out-turn position for 2016/17, set out in Table 1 of the report and Appendix 1 to the report, be noted. (2) That the additional capital expenditure at Waterside, detailed in paragraph 3.6 of the report, be approved. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM:OD)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Budget Management Update Cabinet Date: 26th April 2017
Authors: Cabinet Member for Finance and Corporate Services and Corporate Director for Resources and Transformation Wards: All Locality Affected: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report presents the 2016/17 Revenue Budget forecast out-turn and a capital programme update. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 1.3 Responsible budget management underpins the Council’s strategic objective of consistently making the best use of all available resources as well as providing focus for the Council’s transformation programme. 2. Recommendations Cabinet is recommended to: 2.1 Note the projected Revenue Budget out-turn position for 2016/17 set out in Table 1 and Appendix 1. 2.2 Approve the additional capital expenditure at Waterside as set out in paragraph 3.6. 3. Detail 2016/17 Projected Revenue Out-turn 3.1 It is forecast that the Council’s overall budget will be balanced for the financial year. This reflects the impact of the revised approach for the repayment of debt, approved by Council in February 2017, which will improve the in-year position by £5.5m (Council Minute 87, 2016/17 refers). 3.2 The other significant changes since the last report to Cabinet are: 3.2.1 An improvement of the forecast within Communities and Place of £106k, reflecting a favourable movement across a number of services; 3.2.2 Additional income of £97k within Economy.
Further information on the subject of this report can be obtained from Mick Bowden on Direct Dial No. [phone removed] or Email [email protected] Budget Management Update Cabinet Date: 26th April 2017
3.3The budget and projected out-turn by Department is set out in Table 1 below, with a more detailed analysis is set out in Appendix 1. Table 1 – Projected Out-turn By Department
Department Budget Full-Year Projected Movement 2016/17 Projected Variance since last Outturn report £'000 £'000 £'000 £'000 Adult Services 72,594 77,269 4,675 13 Children Services 26,391 28,162 1,771 (38) Communities and Place 28,137 32,032 3,895 (106) Economy (871) (736) 135 (99) Chief Executive 4,226 4,142 (84) (1) Resources 20,037 18,825 (1,212) (92) Corporate (15,288) (24,468) (8,739) (5,500) Total General Fund 135,226 135,667 441 (5,823) (before one-off resources)
Budget Risks 3.4 The previous report to Cabinet highlighted the continuing pressures within Adult Social Care. The final position on the budget will form part of the assessments undertaken to close the Council’s accounts, particularly around the allocation of costs and income with partner organisations. 3.5 Based on the position above it is currently anticipated that under £0.5m of the £2.6m one-off resources approved by Cabinet in July 2016 will be needed to support the 2016/17 budget (Cabinet Minute 26, 2016/17 refers). Capital Programme Update 3.6 At its meeting on 16 June 2016, Cabinet approved £1m for improvement and drainage works at Waterside Park. The extent of the improvement works and poor condition of the drainage system is far worse than originally thought. The work needs to be carried out urgently to ensure that the Council operates within the Environment Agency licence and Thames Water Discharge license. An additional £900k capital investment is required to complete these works. Cabinet approved the use of 2015/16 and 2016/17 Community Infrastructure Levy receipts to help fund the programme of works at Waterside depot (Cabinet Minute 87(g), 2016/17 refers) and a total of £306k has been received to date (£32k in 15/16 and £274k 16/17). In addition, a section 106 contribution of £203k can be utilised to support this scheme. The balance, amounting to £391k, would need to be met from borrowing.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.