Resolved – (1) That the projected Revenue Budget out-turn position for 2017-18, set out in Table 1 and Appendix 1 of the report, be noted. (2) That the use of the budget risk contingency of £4.183m to mitigate the projected shortfall arising on the high risk savings proposals be approved. (3) That the virements set out in Appendix 2 to the report, be approved. (4) That the use of the capital reserve to meet the infrastructure costs of establishing the new libraries operating model, as set out in paragraphs 3.12 and 3.13 of the report, be approved. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM:FF)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Budget Management Update Cabinet Date: 12th July 2017
Author: Cabinet Member for Finance and Commercialisation and Corporate Director for Resources and Transformation Wards: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report presents the 2017-18 revenue budget forecast out-turn and a capital programme update. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 1.3 Responsible budget management underpins the Council’s strategic objective of consistently making the best use of all available resources. 2. Recommendations Cabinet is recommended to: 2.1 Note the projected revenue budget out-turn position for 2017-18 set out in Table 1 and Appendix 1; 2.2 Approve the use of the budget risk contingency of £4.183m to mitigate the projected shortfall arising on the high risk savings proposals; 2.3 Approve the virements set out in Appendix 2; and 2.4 Approve the use of the capital reserve to meet the infrastructure costs of establishing the new libraries operating model as set out in paragraphs 3.12 and 3.13 3. Detail 2017-18 Projected Revenue Out-turn 3.1 It is forecast that unless mitigating actions are undertaken, the Council’s overall budget would be overspent by £5.6m for the financial year. Details of the steps the Council is taking to reduce the overspend will be reported to subsequent Cabinet meetings. 3.2 The budget and projected out-turn by Department is set out in Table 1 below, with a more detailed analysis is set out in Appendix 1.
Further information on the subject of this report can be obtained from Mick Bowden, Direct Dial [phone removed], or e-mail [email protected]. Budget Management Update Cabinet Date: 12th July 2017
Table 1 – Projected Out-turn By Department
Department Budget Full-Year Projected 2016/17 Projected Variance Outturn £'000 £'000 £'000 Adult Services 82,201 82,531 150 Children Services 28,970 29,477 507 Communities and Place 27,627 28,157 530 Economy (2,047) (1,997) 50 Resources 23,688 23,688 0 Corporate (23,975) (19,569) 4,406 Total General Fund 136,464 142,107 5,643
3.3This position reflects the current status of budget proposals set out in Table 2 below that were identified as high risk in the Council’s budget report, approved by Full Council in February 2017 (Council Minute 87(1), 2016-17 refers). 3.4 These savings were identified as high risk, reflecting both the inherent complexity of the proposals and the progress of the actions needed to deliver the savings. A budget risk contingency budget of £4.183m was therefore established to manage these risks. Table 2 – Status of Key Budget Risks
Proposal Saving Achieved Value at Comment to date Risk £m £’000 £’000 Procurement 500 0 500 Work is underway to identify saving opportunities in addition to those built in to service budget proposals. Digitisation 500 57 443 Proposals are being developed; however, there is a lead-in time to the delivery of this type of saving. Small scale housing 3,000 290 2,710 This reflects inherent risks development around timing of delivery. Headcount 1,500 747 753 A part-year saving achieved reduction from first phase of the headcount reduction programme. Projected Shortfall 4,406
Further information on the subject of this report can be obtained from Mick Bowden, Direct Dial [phone removed], or e-mail [email protected]. Budget Management Update Cabinet Date: 12th July 2017
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.