Resolved – (1) That the report and the progress being made towards achieving the Vision Pledge be noted. (2) That the Corporate Director, Resources and Growth, in consultation with the Cabinet Member for Strategic Planning and Sustainability be authorised to: a) facilitate the deployment of the 20th base station to complete the coverage of the 4GLTE network b) issue a letter of variation to BDUK that will encompass the contract change concerning the reduction in the number of base stations to be used in North Swindon and the associated reduction in the value of the contract (3) That the Cabinet Member for Strategic Planning and Sustainability be authorised to inform Council about the response to its resolution as soon as is practicable. The reasons for the decision and alternative options are as set out in the report to the meeting.
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Superfast Broadband Extension Programme Cabinet Date: 7th February 2018
Author: Cabinet Member for Strategic Planning and Sustainability Corporate Director, Resources and Growth Wards: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report seeks to inform Cabinet about the work being undertaken to provide superfast broadband to rural parts of the Borough and to update Cabinet on securing ultrafast broadband to support the local economy. 1.2 The report is a response to Council’s resolution of 13th July 2017 as well as an opportunity to report progress towards achieving part of the Council’s Vision, Priorities, and pledges. 1.3 This report relates specifically to Pledge 1 of the Council’s Vision: ‘Deliver the Government standard Superfast Broadband coverage to all commercial and domestic premises in the Borough by 2017’. It also contributes to the corporate policy goal to secure ‘right skills, right jobs in the right places’. 2. Recommendations Cabinet is recommended to: 2.1 Note the report and the progress being made towards achieving the Vision Pledge. 2.2 Authorise the Corporate Director, Resources and Growth, in consultation with the Cabinet Member for Strategic Planning and Sustainability: 2.2.1 To facilitate the deployment of the 20th base station to complete the coverage of the 4GLTE network 2.2.2 To issue a letter of variation to BDUK that will encompass the contract change concerning the reduction in the number of base stations to be used in North Swindon and the associated reduction in the value of the contract 2.3 Authorise the Cabinet Member for Strategic Planning and Sustainability to inform Council about the response to its resolution as soon as is practicable.
Further information on the subject of this report can be obtained from Andrew Woods, Tel 01793 46 3714, [email protected]. Superfast Broadband Extension Programme Cabinet Date: 7th February 2018
3. Detail Background 3.1 In May 2015, following an open tender process the Superfast Broadband Extension Programme Contract was awarded to UKB Networks (UKBN) for a value of £1.9m, funded equally by the Council and BDUK. The outcome required from the Contract is to provide superfast broadband (above 25mbps) to over 19,500 homes that could not access superfast speeds. 3.2 In September 2015, the Council adopted a Vision including the specific pledge to secure access to the government standard superfast broadband across the Borough (Council Minute 33, 2015/16 refers). 3.3 At the Council meeting of 13th July 2017, Members resolved (Council Minute 21, 2017/18 refers): “This Council: Notes that: a) A modern, vibrant economy needs access to fast broadband, and b) Before the Council signed the contract with UK Broadband Networks Ltd there was no direct interest in expanding fibre networks across Swindon from the private sector. Welcomes: a) That hundreds of residents now have access to faster broadband; b) That decisive action form the Conservative Council has stimulated the market; c) The investment made by Virgin and BT in rolling out fibre broadband thanks to the support of local residents, Conservative Councillors and Conservative MPs over many years; and d) The exciting news that Swindon is a test bed for both G-Fast and 5Ga broadband. Council asks the Cabinet Member for Strategic Planning and Sustainability to bring a report to Cabinet: (a) Setting out the costs and benefits so far, particularly in rural areas, and the additional activity by the private sector to provide broadband since the Council’s decision; and
Further information on the subject of this report can be obtained from Andrew Woods, Tel 01793 46 3714, [email protected]. Superfast Broadband Extension Programme Cabinet Date: 7th February 2018
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.