Resolved – (1) That the forecast capital expenditure, set out in Table 1 & 2 of the report and Appendix 1 to the report, be noted. (2) That the changes detailed at paragraphs 3.2 to 3.3 of the report be noted and that the required funding adjustments be approved. (3) That the additions to the programme, set out at section 3.4 of the report, be approved. (4) That the changes to the HRA capital programme, detailed at paragraph 3.5 of the report, be noted, and that the required funding adjustments be approved. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM:DH)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Capital Monitoring Quarter 3 2018/19 Cabinet Date: 20th March 2019
Authors: Cabinet Member for Finance Director of Finance Wards: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report presents the third quarter’s monitoring position for the Council’s capital programme and some proposed changes to the programme. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 1.3 Responsible budget management underpins the Council’s strategic objective of consistently making the best use of all available resources as well as providing focus for its change programmes. 2. Recommendations Cabinet is recommended to: 2.1 Note the forecast capital expenditure set out in Table 1 & 2 and Appendix 1, 2.2 Note the changes detailed at paragraphs 3.2 to 3.3 and approve the required funding adjustments 2.3 Approve the additions to the programme noted at section 3.4. 2.4 Note the changes to the HRA capital programme detailed at paragraph 3.5 and approve the required funding adjustments 3. Detail Capital Programme – 2018/19 monitoring 3.1 Table 1 below shows the current status of the 2018/19 capital budget and forecast outturn position. The significant budget movements are detailed in paragraphs 3.3 to 3.5 below. Table 2 shows how the capital programme is being funded.
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Quarter 3 2018/19 Cabinet Date: 20th March 2019
Table 1 - Budget Forecasts and Variances Service Budget Forecast Projected Remaining Scheme Variances 2018/19 Spend to Onwards Completion Group £’000 £’000 £’000 Community Works 1,174 1,035 (139) Corporate Projects 66,162 67,100 938 Section 106 9,329 9,329 - Schools 16,598 16,694 96 Social Care 1,250 1,250 - Transport 110,623 110,623 - Total General Fund 205,136 206,031 895 HRA 64,213 64,418 205 Service Totals 269,349 270,449 1,100 New approvals - 2,514 2,514 Revised Total programme 269,349 272,963 3,614
Table 2 - Capital Programme funding Current New Amended Funding Funding Funding Requirement Required Requirement £'000 £'000 £'000 Balance to be financed: 269,349 3,614 273,420 Capital Receipts 11,193 119 11,312 Section 106 Deposits 11,942 11,942 Grant Funding 130,973 690 131,663 Revenue Contributions 9,568 4 9,572 HRA balances 37,673 205 37,878 Salix funding (Interest free loan) 6,000 6,000 Invest to save borrowing repaid 420 420 from future revenue budgets Increase in Borrowing Requirement 62,000 2,176 64,176 Total 269,349 3,614 272,963 There is a revenue impact from the additional borrowing of circa £174k
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Quarter 3 2018/19 Cabinet Date: 20th March 2019
Projected Variances 3.2 Cabinet is asked to note the following variances to projects within the capital programme. Appendix 1 contains details of all schemes in the capital programme, including those highlighted in previous Cabinet reports, together with their forecast closing position. Cabinet has not previously been advised of variances on the schemes noted below: 3.2.1 Underspends / removals from the current programme
Grounds maintenance equipment (line 3) – underspend of £139k related to procurement savings reducing the need for borrowing.
Self-Build scheme (line 45) budget £457k. Officers are proposing that this scheme is removed as it is not a project that is being actively progressed. 3.2.2 Schools programme total overspend of £96k funded from Education Basic Need Grant.
Orchid Vale PFI expansion (line 102) – underspend of £40k, the project is now complete and final accounts are being agreed.
Brimble Hill expansion (line 93) ) – overspend of £36k as a result of a revised estimate being provided by the contractor
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.