Resolved

- 1) That the latest 2018/19 Capital Programme position as at financial year end as detailed in paragraphs 3.1 to 3.4 be noted. 2) That the changes to the programme in sections 3.5 to 3.6 be approved. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: RH)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet

Capital Monitoring Outturn 2018/19 Cabinet Date: 5th June 2019

Authors: Cabinet Member for Finance, Education and Skills Director of Finance Wards: All Parishes Affected: All

1. Purpose and Reasons 1.1 This report presents the capital programme position as at the end of 2018/19 and proposed changes to the programme. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 1.3 Responsible budget management underpins the Council’s strategic objective of consistently making the best use of all available resources as well as providing focus for its change programmes. 2. Recommendations Cabinet is recommended to: 2.1 Note the latest 2018/19 Capital Programme position as at financial year end as detailed in paragraphs 3.1 to 3.4. 2.2 Approve the changes to the programme in sections 3.5 to 3.6. 3. Detail Capital Programme – 2018/19 monitoring 3.1 Table 1 below provides a summary of the out-turn position (“forecast spend to completion” column) compared with the approved total scheme budgets, as at the end of March 2019. The projected out-turn position represents the expected total spend for the scheme to completion over all remaining years. Table 2 shows how the capital programme is expected to be funded.

Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Outturn 2018/19 Cabinet Date: 5th June 2019

Table 1 - Budget Forecasts and Variances

Service Budget Forecast Projected Remaining Scheme Variances 2018/19 Spend to Onwards Completion Group £’000 £’000 £’000 Community Works 1,035 1,035 - Corporate Projects 69,754 70,092 338 Section 106 (S106) 9,330 9,330 - Schools 17,687 17,687 - Social Care 1,250 1,250 - Transport 111,955 111,955 - Total General Fund 211,011 211,349 338 HRA 64,056 64,056 - Total Existing Programme 275,067 275,405 338 New Approvals 236 236 236 Revised Total programme 275,303 275,641 574

Table 2 - Capital Programme funding

Current New Funding Amended Funding Required Funding Requirement Requirement £'000 £'000 £'000 Capital Receipts 11,312 - 11,312 Section 106 Deposits 10,493 236 10,729 Grant Funding 131,455 - 131,455 Revenue Contributions 9,568 - 9,568 HRA balances 37,516 - 37,516 Salix funding (Interest free loan) 6,000 6,000 Invest to save borrowing repaid 420 - 420 from future revenue budgets Increase in Borrowing 68,579 338 68,877 Requirement Total to be financed 275,303 574 275,877 There is a revenue impact from the additional borrowing of circa £27k

Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Outturn 2018/19 Cabinet Date: 5th June 2019

3.2The total spend incurred in 2018/19 and how it was funded is shown below: Table 3: Capital Expenditure Funding

£’000s Actual Capital Spend 2018/19 75,039 Funded by: Capital Receipts 4,045 S106 Deposits 5,224 Grant 21,800 HRA balances 18,849 CIL 1,340 Increase in Borrowing Requirement 23,781 Total 75,039

3.3The detailed capital monitoring for 2018/19 is attached at Appendix 1.

Projected Variances

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
OutturnAppendix 1 187 KB Download
PDF
Capital Programme Monitoring Out-Turn 2018/19Report 239 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. Capital Programme Monitoring Out-Turn 2018/19This decision
  2. Capital Programme 2026/2027 (Minute for Confirmation)Approved
  3. Capital Programme 2025-2026Approved
  4. Capital Programme 2024/2025 (Minute for Confirmation)Approved
  5. Capital programme 2023-24 (Minute for Confirmation)Approved
  6. Capital Programme to 2026/27 (Minute for Confirmation)Approved

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies