- 1) That the forecast capital expenditure set out in Table 1 & 2 and Appendix 1 and 2 be noted; 2) That the changes detailed at paragraphs 3.2 to 3.3 be noted and the required funding adjustments approved; 3) That the additions to the programme noted at section 3.4 be approved . The reasons for the decision and alternative options are as set out in the report to the meeting. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: DR/OD)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Capital Monitoring Quarter 1 2019/20 Cabinet Date: 4th September 2019
Authors: Cabinet Member for Finance, Education and Skills Director of Finance Wards: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report presents the first quarter’s monitoring position for the Council’s capital programme and some proposed changes to the programme. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 1.3 Responsible budget management underpins the Council’s strategic objective of consistently making the best use of all available resources as well as providing focus for its change programmes. 2. Recommendations Cabinet is recommended to: 2.1 Note the forecast capital expenditure set out in Table 1 & 2 and Appendix 1 and 2, 2.2 Note the changes detailed at paragraphs 3.2 to 3.3 and approve the required funding adjustments 2.3 Approve the additions to the programme noted at section 3.4. 3. Detail Capital Programme – 2019/20 monitoring 3.1 Table 1 below shows the current status of the 2019/20 capital budget and forecast outturn position. Please note that this table now includes the historic spend on projects that span more than 1 year. The significant movements are detailed in paragraphs 3.2 to 3.4 below. Table 2 shows how the capital programme is being funded.
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Quarter 1 2019/20 Cabinet Date: 4th September 2019
Table 1 - Budget Forecasts and Variances
Forecast Total Projected Projected Scheme Scheme Overspend Underspend Service Area Spend to Budget Completion £000's £000's £000's £000's Resources 53,027 53,027 Economy 112,645 112,679 34 Children Services 28,436 28,442 6 Adult Services 8,766 8,766 Communities & Housing 112,418 112,754 560 (224) Total General Fund 315,292 315,668 600 (224) HRA 95,632 93,581 (2,051) Total Existing Programme 410,924 409,249 600 (2,275) New Approvals 3,912 3,912 Revised Total programme 414,836 413,161 600 (2,275)
Table 2 - Capital Programme funding
Total Funded Funding Revised Funding to still Funding Total Required 31/3/19 required Changes Funding £000's £000's £000's £000's £000's
Capital Receipts 6,417 5,014 1,403 6,417 Section 106 Deposits 20,627 7,474 13,153 3,264 23,891 Grant Funding 134,772 38,427 96,345 150 134,922 Revenue Contributions 3,247 127 3,120 3,247 HRA balances 79,783 23,608 56,175 (2,051) 77,732 Salix funding (Interest free loan) 6,000 6,000 6,000 Invest to save borrowing repaid 24,888 24,888 24,888 from future revenue budgets Increase in Borrowing 135,190 48,034 87,156 874 136,064 Requirement Total to be financed 410,924 122,684 288,240 2,237 413,161
Projected Variances
3.2Cabinet is asked to note the following new variances to projects within the capital programme. Appendix 1 contains a summary of the current capital programme and Appendix 2 contains the details of the individual schemes in the capital programme, together with their forecast closing position.
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Quarter 1 2019/20 Cabinet Date: 4th September 2019
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.