(1) That the 2019/20 year end position of the capital programme expenditure as set out in Tables 1 & 2 of the main report and Appendices 1 and 2 be noted. (2) That it be noted that there are no new variances to the programme as they have all been reported to Cabinet at previous meetings; (3) That the addition to the programme of a) £429k for Coate Water Country Park Improvements funded from S106 contributions and b) £2.016m for Highway maintenance including pothole repairs, carriageway resurfacing and traffic signal refurbishment funded through grant funding from the new Transport Infrastructure Investment Fund as detailed at paragraph 3.7 of the main report be approved. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: RH)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Capital Monitoring Outturn 2019/20 Cabinet Date: 1st July 2020
Author: Cabinet Member for Commercialisation, Education, and Skills Corporate Director of Finance and Assets Wards: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report presents the 2019/20 year end monitoring position for the Council’s capital programme and some proposed changes to the programme. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 2. Recommendations Cabinet is recommended to: 2.1 Note the 2019/20 year end position of the capital programme expenditure as set out in Tables 1 & 2 of the main report and Appendices 1 and 2; 2.2 Note that there are no new variances to the programme as they have all been reported to Cabinet at previous meetings; 2.3 Approve the addition to the programme of a) £429k for Coate Water Country Park Improvements funded from S106 contributions and b) £2.016m for Highway maintenance including pothole repairs, carriageway resurfacing and traffic signal refurbishment funded through grant funding from the new Transport Infrastructure Investment Fund as detailed at paragraph 3.7; 3. Detail Capital Programme Outturn 3.1 Table 1 below shows the expenditure incurred in delivering the 2019/20 capital programme. Table 2 shows how the 2019/20 expenditure will be funded 3.2 Completed schemes as shown in table 1 are those that have previously been reported to Cabinet as the project having been completed during the year. Schemes that budget managers have now notified as complete as at year end will be removed from the capital programme reports for 2020/21.
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Outturn 2019/20 Cabinet Date: 1st July 2020
Table 1 - Total expenditure in 2019/20
General In year HRA Service Area Fund spend £000's £000's £000's Resources 19,112 19,112 Economy 17,307 17,307 Children Services 8,487 8,487 Adult Services 1,321 1,321 Communities & Housing 11,690 11,690 Total General Fund 57,917 57,917 HRA 16,323 16,323 Completed Schemes 26 64 90 Total Existing Programme 57,943 16,387 74,330
Table 2 –Funding for 2019/20 expenditure
General Total HRA Funding Source Fund Funding £000's £000's £000's Capital receipts 1,459 1,459 Section 106 Deposits 3,112 40 3,152 Grant 33,551 1,492 35,043 HRA revenue 5,812 5,812 HRA balances 7,584 7,584 CIL 1,102 1,102 Borrowing Requirement 20,178 20,178 Total to be financed 57,943 16,387 74,330
3.3Table 3 below shows the current status of the overall approved capital programme for 20/21 and beyond and the forecast outturn position. Table 4 shows how this is being funded. 3.4 The capital programme report includes items that were agreed at Council on 20 th February 2020 (draft Council Minute 80, 2019/20 refers). Any over or under spends will affect the overall funding sources for the capital programme. 3.5 Completed schemes as shown in table 3 are those schemes that have incurred expenditure up to and including 19/20 previously identified as complete by project managers. These will be removed from the 20/21 capital programme together with any further schemes identified as complete at year end.
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Outturn 2019/20 Cabinet Date: 1st July 2020
Table 3 - Budget Forecasts and Variances
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.