Resolved : (1) That it be agreed in principle to the introduction of a Street Works Permit Scheme subject to consultation and to note the detail of the scheme be determined by the cabinet member for Highways, Maintenance and Waste Services (2) That the Director of Strategic Development be authorised to proceed with a consultation, as prescribed under Regulations, to introduce a Street Works Permit Scheme into Swindon. The reasons for the decision and alternative options are as set out in the report to the meeting. (Councillor Brian Ford, Cabinet Member for Adults and Health, left the meeting at the end of this item.) (CM: RH)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
2.1Agree in principle to the introduction of a Street Works Permit Scheme subject to consultation and to note the detail of the scheme be determined by the cabinet member for Highways, Maintenance and Waste Services
2.2Authorise the Director of Strategic Development to proceed with a consultation, as prescribed under Regulations, to introduce a Street Works Permit Scheme into Swindon.
3. Detail
Roadworks in Swindon
3.1Swindon has a road network comprising nearly 580miles of length, of which 91% (525 miles) comprise minor roads and 10% comprise principal or trunk roads. There are 9.5 miles of motorway (M4) running through the area.
3.2In 2019, 6,676 utility works were undertaken across Swindon, resulting in over 31,000 days with highway occupation. It is estimated that an additional 5,170 Council works are undertaken during an average year resulting in 3,500 of highway occupation.
3.3In an average year the Council receives 16,000 applications to work in the highways per year, with 47,000 days of combined occupation of the highways. This volume of works
Further information on the subject of this report can be obtained from Syed Shah, [phone removed], [email protected]. Introduction of a Permit Scheme for Roadworks Cabinet Date: 3rd February 2021
would equate to an average of 28 works starting each day of the year, averaging 1.2 every hour.
3.4Using sophisticated programs, the following cost impact to society of these works can be estimated:
3.4.1 Road user travel time (delay caused to consumer and business);
3.4.2 Road user vehicle operating costs (the impact of delay and diversion on vehicle operating costs for consumers and business);
3.4.3 Accident costs;
3.4.4 Emissions costs (resulting from congestion and diversion); and
3.4.5 Indirect tax revenue (increased tax revenue to the exchequer because of higher fuel consumption).
3.5The average annual impact of works in the area resulting from road user travel delay, vehicle operating costs and wider effects stands at £15.4 million per annum. The average daily cost impact of works is an estimated £362, while the average work impact cost is an estimated £1,515.
Permit Schemes
3.6Under the Traffic Management Act 2004 (‘The Act’), the Council has a statutory network management duty described as ‘…managing the road network with the aim of securing the expeditious movement of traffic…’. The Act is clear that traffic means all road users, including pedestrians and cyclists, not just motorised vehicles.
3.7The overall objective of the duty is the efficient operation of the network, as a whole, and allows the Council (as a Highway Authority) to act, under legislative controls, to deliver this objective.
3.8The Act and associated secondary regulations widened existing legislation for the coordination of activities and works on the road network; Part 3 of The Act allows the Council to introduce a permit scheme to support the delivery of their duty.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.