(1) That the 2020/21 year end projected out-turn position as set out in Tables 1 & 2 and Appendices 1 and 2 be noted; (2) That the amendments following to the current approved capital programme budgets as detailed at paragraph 3.2 of the joint report be approved : (a) To reduce the IT infrastructure budget (line 7) budget by £29k to reflect revised cost of the project; (b) To reduce the William Morris Primary School budget (line 36) budget by £400k to reflect revised cost of the project; (c) To reduce the Regulatory & Statutory Services Case Management System budget ( line 167) budget by £3k to reflect revised cost of the project; (d) To note that Mead Way (line 163) is currently forecasting an overspend of £475k, and that officers are in contractual negotiations as well as reviewing other budgets to mitigate this position; and (e) To remove the £3.5m capital contingency fund budget (line 3). (3) That the following addition to the programme detailed at paragraph 3.4 be approved and it be noted that this further update to the Capital Programme can be accommodated within the approved capital financing revenue budget and prudential indicators as set out in the 2020/21 Budget approved by Council. (a) That £585k of grant funding be allocated to improve cycling provision in the town centre and Old Town. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: MP, GS)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
2.1Note the 2020/21 year end projected out-turn position as set out in Tables 1 & 2 and Appendices 1 and 2;
2.2Approve the amendments to the current approved capital programme budgets as detailed at paragraph 3.2:
2.2.1 To reduce the IT infrastructure budget (line 7) budget by £29k to reflect revised cost of the project;
2.2.2 To reduce the William Morris Primary School budget (line 36) budget by £400k to reflect revised cost of the project;
2.2.3 To reduce the Regulatory & Statutory Services Case Management System budget (line 167) budget by £3k to reflect revised cost of the project;
2.2.4 To note that Mead Way (line 163) is currently forecasting an overspend of £475k, and that officers are in contractual negotiations as well as reviewing other budgets to mitigate this position; and
2.2.5 To remove the £3.5m capital contingency fund budget (line 3).
2.3Approve the additions to the programme detailed at paragraphs 3.4. This further update to the Capital Programme can be accommodated within the approved capital financing revenue budget and prudential indicators as set out in the 2020/21 Budget approved by Council.
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Outturn Q3 2020/21 Cabinet Date: 3rd March 2021
2.3.1 To allocate £585k of grant funding to improve cycling provision in the town centre and Old Town.
3. Detail
Capital Programme Outturn
3.1Table 1 below shows the current status of the 2020/21 capital budget and forecast outturn position. The significant budget movements are detailed in paragraph 3.2 below. Table 2 shows how the capital programme is being funded.
Table 1 - Total expenditure in 2020/21 Total Projected Projected Projected Scheme Service Area Out-turn Overspends Underspends Budget £000's £000's £000's £000's Resources - Enabling 8,098 8,069 (29) Resources - Finance & Assets 53,572 53,572 Resources - Operations 16,661 16,661 Children Services 24,736 24,236 (500) Adults, Housing & Public Health 13,515 13,515 Economy & Development 283,431 284,597 1,169 (3) Total General Fund 400,013 400,650 1,169 (532) HRA 179,975 179,975 Total Existing Programme 579,988 580,625 1,169 (532) New Approvals 585 585 Revised Total programme 580,573 581,210 1,169 (532)
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Outturn Q3 2020/21 Cabinet Date: 3rd March 2021
Table 2 - Capital Programme funding Total Funded to Additional Revised Funding still Funding 31/3/20 Funding Total required Required Required Funding £000's £000's £000's £000's £000's Capital Receipts 16,742 3,253 13,489 (29) 16,713 Section 106 Deposits 37,466 6,509 30,957 37,466 Grant Funding 201,059 41,054 160,005 560 201,619 Revenue Contributions 3,408 1,409 1,999 3,408 HRA balances 165,925 18,209 147,716 165,925 Invest to save borrowing repaid from future revenue 1,468 1,468 1,468 budgets Change in Borrowing 153,920 33,766 120,154 691 154,611 Requirement Total to be financed 579,988 104,200 475,788 1,222 581,210
Projected Variances
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.