Final Report of the Task Group - Oasis Closure and Potential Re-opening
DecidedCommittee2 papers
Task Group - Oasis closure and potential reopening decided this item on Thursday 2 September 2021. Below is the council's own wording, with the papers it was decided on.
(1) To endorse the draft Final Report of the Task Group on the Oasis Closure and potential re-opening, as attached at Appendix 1, for submission to the Scrutiny Committee at its meeting on 13 th September 2021 with no amendments. (2) To place on record its sincere thanks to the people who volunteered their time to answer questions for the Task Group, to the officers who supported the Task Group, and to the residents who took the time to contact Councillors and detail their questions and concerns about the Oasis and its future.
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Report to Task Group - Oasis closure and potential reopening, 3 pages
Recommendations
The Task Group is recommended to:
2.1Consider the draft Final Report of the Task Group on the Oasis Closure and potential re- opening as attached at Appendix 1.
2.2Agree that the Clerk, in consultation with the Chair of the Group, be authorised to make any changes to the Final Report as a result of amendments agreed at this meeting, for submission to the Scrutiny Committee at its meeting on 13th September 2021.
2.3Place on record its sincere thanks to the people who volunteered their time to answer questions for the Task Group, to the officers who supported the Task Group, and to the residents who took the time to contact Councillors and detail their questions and concerns about the Oasis and its future.
3. Detail
3.1At its meeting on 21st January 2021, Council passed a Resolution concerning the Oasis (Minute 71, 2020/21 refers). As part of the debate, the Chair of the Scrutiny Committee undertook to request that the Scrutiny Committee also investigate the issues.
3.2At its meeting on 8th February 2021, Scrutiny Committee resolved to add to its Work Programme a cross-party Task Group (Minute 54 2020/21 refers).
3.3The Task Group were invited to consider the following as its purpose for the review:
3.3.1 Investigate the circumstances that led to the closure of the Oasis and the options that are open to the Council to ensure its reopening after lockdown.
Further information on the subject of this report can be obtained from Vicki Yull (Committee Officer), [phone removed], [email protected]. Draft Final Report of the Task Group – Oasis Closure and Potential Re- opening Scrutiny Committee Task Group Date: 2nd September 2021
3.3.2 Investigate the £3m payment that was made from the Council to GLL, any obligations placed on GLL around this money, and whether the Council should seek to have any of the payment repaid.
3.3.3 Investigate the deal with SevenCapital which included the transfer of the land at the former Clare’s Site, seeking to determine what obligations were put on SevenCapital to deliver the Snowdome and the protection of the Oasis Leisure Centre.
3.3.4 The break clauses open to the Council to return the land and the Oasis to Council control.
3.4The Task Group met on 16th February 2021 and interviewed:
3.4.1 Councillor David Renard, Leader of the Council.
3.4.2 Councillor Keith Williams, Cabinet Member for Climate Change (who oversaw the leisure options transfer at the time).
3.4.3 [name removed] and [name removed] from SevenCapital.
3.4.4 [name removed] and [name removed] from GLL.
3.4.5 [name removed] (former Councillor and Leader of the Council).
3.5The Task Group met on 18th March 2021 and interviewed:
3.5.1 Councillor David Renard.
3.5.2 [name removed], former Council employee and involved in the leisure options project at the time.
3.6The Task Group also considered reports and legal documents relating to the Oasis which had been produced since prior to the leisure options transfer in 2012.
3.7Following those meetings, the Chair has drafted the Final Report of this Task Group which is attached at Appendix 1 to this report. Members are invited to discuss its contents and agree on a final version for submission to Scrutiny Committee for consideration at its meeting on 13th September 2021.
Alternative options
4.1None.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Task Group - Oasis closure and potential reopening at Swindon and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.