Resolved
Resolved - That the report be noted and Officers be thanked for their presentation and responses to Members’ questions.
Communities and Place Overview and Scrutiny Committee noted this item on Wednesday 28 September 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved - That the report be noted and Officers be thanked for their presentation and responses to Members’ questions.
2.1To note the content of the report and the process undertaken to adopt a highway as a pubic asset.
3. Detail
3.1This report has been prepared to clarify the approval, inspection and adoption process for prospective highway assets, whether negotiations on Section 38 agreements can be undertaken earlier, and best practice.
3.2In order to reduce the timescale involved in completing highway adoption agreement, technical and legal resources could be kept under review, so as to ensure that current and future service needs can be managed (although this might have financial and staffing implications). This is particularly important once house building commences at the NEV and as Wichelstowe continues to progress. It is also important that the Council is able to ensure that Private Street Works monies are secured from an early stage to enable us to carry out Private Street Works where roads are not offered for adoption.
3.3A Section 38 agreement (or S38) is a section of the Highways Act 1980 that can be used when a developer proposes to construct a new estate road for residential, industrial or general purpose traffic that may be offered to the Highway Authority for adoption as a public highway.
Further information on the subject of this report can be obtained from Syed Shah, [phone removed], [email protected] Adoption of New Estate Roads Communities and Place Overview and Scrutiny Committee Date: 28 September 2022
3.4A section 278 agreement (or s278) is a section of the Highways Act 1980 that allows developers to enter into a legal agreement with the council (in our capacity as the Highway Authority) to make permanent alterations or improvements to a public highway, as part of a planning approval.
3.5Swindon Borough Council, as the Local Highway Authority, have limited powers to request developers to enter into adoption agreements to offer private streets as public highway
3.6The Council’s Transport Development Management is in the final stage of updating the Council’s Transport Requirements for Development, which is currently being formatted to the SBC’s standard document format. This document will be duly consulted upon in the coming months, before being considered for adoption. This updated local design guide document would clarify requirements, specifications and expectations for new development works in the Borough.
3.7Officers are working hard to ensure that highway works associated with new developments are assessed and constructed to the standards required to allow their adoption as a highway asset and that they are progressed efficiently to be adopted as public assets in a timely manner.
3.8Stages of estate road adoption:
3.8.1 Application / Advance Payment Code (APC) process.
3.8.2 Following a development obtaining Planning permission from the Planning Authority a development site may proceed to construction.
3.8.3 An APC notice is issued to the developer subject to the building regulation application process being communicated.
3.8.4 An APC notice must be issued within 6 weeks of application for building consent.
3.8.5 Upon the commencement of plots being constructed the developer is obliged to pay the relevant APC sums.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Adoption of New Estate RoadsReport | 8 pages | DownloadRead as text |
Follow Communities and Place Overview and Scrutiny Committee at Swindon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Feb 2023 | Work Programme 2022/23Resolved – That the report be noted. | Noted | Open |
| 30 Nov 2022 | Network Management PlanResolved – (1) That the report be noted. (2) That the Director of Strategic Development and Growth be requested to su... | Noted | Open |
| 30 Nov 2022 | Communications in Highways and TransportResolved – That the report be noted. | Noted | Open |
| 30 Nov 2022 | Work Programme 2022/23Resolved – That the report be noted. | Noted | Open |
| 28 Sep 2022 | Motion at Council - Highway WorksResolved - That the report be noted and Officers be thanked for their presentation and responses to Members’ questions. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.