(1) That the 2022/23 year-end projected out-turn position as set out in Tables 1 & 2 and Appendices 1 and 2 be noted. (2) That the new significant budget variances set out at paragraph 3.3 be noted. (3) That the amendments and additions to the programme detailed at paragraphs 3.4 be approved and that it be noted that the additions can be accommodated within the approved capital financing revenue budget and prudential indicators as set out in the 2022/23 Budget approved by Council. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: DR)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
2.1Note the 2022/23 year-end projected out-turn position as set out in Tables 1 & 2 and Appendices 1 and 2.
2.2Note the new significant budget variances set out at paragraph 3.3.
2.3Approve the amendments and additions to the programme detailed at paragraphs 3.4 noting that the additions can be accommodated within the approved capital financing revenue budget and prudential indicators as set out in the 2022/23 Budget approved by Council.
3. Detail
Capital Programme Outturn
3.1Table 1 below shows the expenditure incurred in delivering the existing capital programme. The significant variations are detailed in paragraph 3.3. Table 2 shows how the capital programme, including proposed new approvals, is being funded.
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Outturn Q1 2022/23 Cabinet Date: 12th October 2022
Table 1 - Approved Capital Programme Projected Projected Projected Total Scheme Service Area Out-turn Overspends Underspends Budget £000's £000's £000's £000's Resources - Enabling 2,821 2,821 Resources - Finance & Assets 55,532 55,209 (323) Resources - Operations 21,992 21,992 Children Services 25,923 25,923 Adults, Housing & Public Health 16,276 16,078 (198) Economy & Development 309,319 324,610 15,295 (4) Total General Fund 431,863 446,633 15,295 (525) HRA 189,313 189,313 Total Existing Programme 621,176 635,946 15,295 (525) New Approvals 4,432 4,432 Revised Total programme 625,608 640,378 15,295 (525)
Table 2 - Capital Programme funding Total Funding Funded to Funding still Required 31/3/22 required £000's £000's £000's Capital Receipts 3,349 3,253 96 Section 106 Deposits 40,695 6,509 34,186 Grant Funding 229,917 41,054 188,863 Revenue Contributions 1,888 1,409 479 HRA balances 140,195 18,209 121,986 CIL 1,050 1,050 Invest to save borrowing repaid from 1,468 1,468 future revenue budgets Change in Borrowing Requirement 221,815 33,766 188,049 Total to be financed 640,378 104,200 536,178
3.2Appendix 1 contains a summary of the current capital programme and Appendix 2 contains the details of the individual schemes in the capital programme, together with their forecast out-turn position. The report is based on the end of August 2022 position, but includes any material forecast changes since then.
Projected Variances
3.3All new significant budget movements that have not already been reported to Cabinet are detailed below.
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Outturn Q1 2022/23 Cabinet Date: 12th October 2022
3.3.1 Package 2 Nythe Road Junction and Piccadilly Roundabout (line 89) – this is reporting an increased overspend of £2.9m (up from £1.4m) due largely to an increased allowance for additional Compensation Events (CE’s) submitted very late by the contractor claiming additional prolongation costs, as well as associated fuel duty and inflation.
3.3.2 Gablecross Junction (line 88) – this is reporting an increased overspend of £1.1m (up from £0.55m) primarily due to further prolongation costs around utility issues and further compensation events for changes of tarmac, additional regulation, re-designs and inflation.
Amendments and additions to current programme
3.4Cabinet is asked to approve the following amendment and additions to the programme
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.