- (1) That Cabinet recommend that Council Approves the Pay and Reward proposal outlined in the body of the text and Appendix 1 for inclusion in the Council’s budget for 2023/24 (2) That Subject to Council approving the budget as set out in recommendation 2 and all the dependencies outlined in 3.22 being satisfied, Cabinet authorise the Head of Paid Service to implement the model as per the plan (3) That, if following the ballot, the recognised trade union request changes to the offer outlined in Appendix 1, Cabinet authorise the Head of Paid Service to make changes to the proposal, in consultation with the Leader of the Council, as long as the whole offer to be covered by Collective Agreement does not exceed the budget agreed and as set out in 5.1.
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Cabinet is recommended to request that Council (Minute for Confirmation):
Approves the Pay and Reward proposal outlined in the body of the text and Appendix (1) for inclusion in the Council’s budget for 2023/24.
Cabinet is recommended to:
Subject to Council approving the budget as set out in recommendation 2 and all the dependencies outlined in 3.22 being satisfied, authorise the Head of Paid Service to implement the model as per the plan.
If, following the ballot, the recognised trade union request changes to the offer outlined in Appendix (1), authorise the Head of Paid Service to make changes to the proposal, in consultation with the Leader of the Council, as long as the whole offer to be covered by Collective Agreement does not exceed the budget agreed and as set out in 5.1.
3. Detail
The pay and reward programme was started back in 2018/2019 with a view to addressing key issues relating to the Council’s pay structure and its terms and conditions for staff. The last review of pay and reward took place in 2010 and since then our pay and reward offer has not kept pace with the market and has been inconsistently applied. This is due to a number of different factors including a lack of rigor in pay setting, failure to review market conditions for pay, changes to Council working practices and resident expectations and significant numbers of
Further information on the subject of this report can be obtained from Sonia Grewal, [email protected]. Pay and Reward Scheme – Next Steps to Implementation Cabinet Date: 1st February 2023
staff being TUPE’d in and out of the organisation over that time on different terms and conditions. To address this the pay and reward programme was set up and seeks to address the following problems:
3.1.1 Issues with retention of staff and reduced operational effectiveness, meaning the Council will have increased reliance on a smaller number of colleagues with increased work burdens.
3.1.2 Reliance on agency staff and increased cost due to this reliance. Current agency costs in Childrens and Adults Social care alone are c.£6m per year.
3.1.3 Market pay erosion of the system leading to a lack of ability to appoint suitably qualified or experienced candidates again leading to operational effectiveness loss over time.
3.1.4 A requirement for greater flexibility in operational practice which is not currently available within the Council’s existing terms and conditions of employment.
3.1.5 Potential risk of equal pay claims has been identified which could lead to exposure for the Council based on the current pay system. This is primarily due to how outdated this is. Equal pay claims could lead to further risks such as:
i. Claims at tribunals leading to volumes of costly legal fees,
ii. Lost productivity from disputes,
iii. Impact to employee relations and lead to low morale.
iv. Cost of tribunal decisions rulings in favour of claimants can be as much as (up to six years of back pay for any difference in pay) where pay issues are identified, leading to a loss and damage to reputation and possible mandatory tribunal ordered pay audits.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.